Configuration Manual — KOSTAL PV Inverter
1. Introduction
Manual 2026.9.1
These instructions are used to configure the following KOSTAL PV inverters for integration into the FEMS:
KOSTAL |
|
2. Prerequisites
Only KOSTAL inverters of the model series mentioned in the Introduction with at least the following firmware versions are supported:
-
PLENTICORE plus
-
UI version: 01.18.05255 or higher
-
MC version: 01.47 or higher
-
IOC version: 01.45 or higher
-
HW version: 0101 or higher
-
-
PIKO IQ
-
UI version: 01.21.06586 or higher
-
MC version: 01.60 or higher
-
IOC version: 01.60 or higher
-
HW version: 0100 or higher
-
-
PIKO CI
-
Latest firmware (at least V3.10 - April 202211.04), see link: KOSTAL download platform
-
You can check the device’s software versions by selecting Info
3. Configuration via the Kostal Web Interface
Before integrating the inverter into FEMS, you should make sure that all necessary preparations have been made.
This includes configuring the inverter via the web interface.
To integrate the device into the FEMS, please configure it via the web interface. You can access this by calling up the IP address of the inverter in the browser. We recommend setting the assignment of the IP address to "Automatic" when commissioning the device.
| To be able to access the web interface, your PC/notebook/smartphone must be in the same network as the inverter. |
3.1. Network
-
Make the following settings here:
-
Obtain an IPv4 address automatically
-
We recommend deactivating DHCP for the inverter in the router settings so that it always retains the same IP address.
3.2. Ping test
To test the configuration, we recommend pinging the inverter in the local customer network.
In the example below, the inverter uses the address 192.168.178.59.
If the inverter cannot be reached via ping, please check the [network] settings.
4. Integrating the PV inverter into FEMS
After you have configured the settings on the PV inverter, you can integrate it into FEMS.
Prepare to install the FEMS App by following these instructions:
-
For the latest versions of FEMS:
-
Navigate to the main menu item
-
Follow these instructions: General Installation Manual for FEMS Apps.
-
After entering the key, you will see the following screen:
|
Some of the input fields are pre-filled. The alias is the name under which the PV inverter is displayed in FEMS. You can choose any name you like, but it should be meaningful. Required fields are marked with an *. |
-
Check the IP address. You can find this either in the web interface of the respective PV inverter or in the list of devices registered on the router (e. g., Fritz!Box). If necessary, adjust the IP address so that they match.
-
The port should be set to 502 in accordance with the standard.
-
For the Modbus Unit ID, if a value has already been set in the PV inverter’s web interface, 123 must be added to that value. Enter this result as the Modbus Unit ID in FEMS.
-
Finally, specify which phase(s) is/are connected to the PV inverter.
Complete the installation by selecting INSTALL APP.
The integration of the PV inverter into FEMS is now complete.