FENECON Home 10 assembly and operating instructions
1. About these instructions
Personnel must have carefully read and understood these Assembly and Service Instructions before starting any work.
1.1. Formal information on the Assembly and Service Instructions
© FENECON GmbH, 2023
All rights reserved
Reprinting, even in part, is only permitted with the permission of FENECON GmbH.
1.2. Version/revision
Version/Revision | Change | Date | Name |
---|---|---|---|
2021.01 |
Draft initial creation |
12.04.2021 |
CE Design |
2021.02 |
Revised draft |
27.05.2021 |
FENECON TK |
2021.03 |
Error correction |
27.06.2021 |
FENECON TK |
2021.04 |
Cable type changed |
05.08.2021 |
FENECON TK |
2021.05 |
Formatting adjusted |
09.09.2021 |
FENECON TK |
2021.06 |
Revision of Inverter and EMS Box |
24.11.2021 |
FENECON FT |
2022.01 |
Insertion of further overviews |
24.11.2022 |
FENECON JE |
2023.01 |
Revision of the instructions |
27.01.2023 |
FENECON JS |
2023.02 |
Conversion to Home 10 Inverter FHI-10-DAH 16A |
07.02.2023 |
FENECON PM |
2024.07 |
Adaptation chapter 8 |
15.07.2024 |
FENECON PM |
2024.09 |
Adaptation of installation conditions and incorrect operation |
19.09.2024 |
FENECON PM |
1.3. Presentation conventions
|
||
|
||
|
||
|
1.4. Structure of warning notices
If observed, warnings protect against possible personal injury and damage to property and use the signal word to classify the magnitude of the danger.
Source of danger |
Danger sign
The danger sign indicates warnings that warn of personal injury test.
Source of danger
The source of danger indicates the cause of the hazard.
Possible consequences of non-compliance
The possible consequences of ignoring the warning are, for example, crushing, burns or other serious injuries.
Measures/Prohibitions
Measures/prohibitions include actions that must be taken to avoid a hazard (e.g. stopping the drive) or that are prohibited to avoid a hazard.
1.5. Terms and abbreviations
The following terms and abbreviations are used in the Assembly and Service Instructions:
Term/Abbreviation | Meaning |
---|---|
AC |
Alternating Current |
BHKW |
Combined heat and power plant (CHP) |
BMS |
Battery Management System |
DC |
Direct Current |
EMS |
Energy Management System |
Energy-Meter |
Electricity meter for the Inverter at the grid connection point |
FEMS |
FENECON Energiemanagementsystem |
IBN |
Commissioning |
MPPT |
Maximum Power Point Tracking — Finder for the maximum power point |
NAP |
Grid connection point |
PE |
Protective conductor |
PV |
Photovoltaic |
RTE |
Round-trip efficiency (RTE) |
SG-Ready |
Smart-Grid-Ready - Preparation of the Heat pump for external control |
SOC |
State of Charge |
SOH |
State of Health - state of ageing |
SPD |
Surge Protection Device - overvoltage protection |
VDE |
Verband der Elektrotechnik Elektronik Informationstechnik e. V. |
Widget |
Component of online monitoring |
1.6. Scope of delivery
Item | Component | Number | Comment |
---|---|---|---|
1 |
FENECON Home 10 - Inverter |
1 |
|
2 |
FENECON Home 10 - EMS Box (incl. FENECON Energiemanagementsystem ) |
1 |
|
3 |
FENECON Home 10 - Parallel Box |
1 |
optional for 2nd FENECON Home 10 battery tower |
4 |
FENECON Home 10 - Extension Box |
1 |
optional for 3rd FENECON Home 10 battery tower |
5 |
FENECON Home 10 - BMS Box |
1 |
per FENECON Home 10 battery tower |
6 |
FENECON Home 10 - Battery module |
depending on the ordered capacity |
|
7 |
FENECON Home 10 - Base |
1 |
per FENECON Home 10 battery tower |
Component | Comment |
---|---|
Installation and service instructions FENECON Home 10 |
Instructions for the installer |
Quick start guide FENECON Home 10 |
Quick start guide for the installer |
Instruction manual FENECON Home 10 |
Instruction manual for the user / end customer |
Brochure FENECON Home 10 |
2. Security
2.1. Intended use
The electricity storage system is used to store electrical energy in rechargeable lithium iron phosphate battery modules (charging) and to provide electrical energy (discharging). This charging and discharging process takes place via a connected FENECON Home 10 inverter. All processes of the electricity storage system are monitored and controlled by the FEMS. The system may only be used in compliance with the permitted technical data (see chapter 3).
2.2. Qualification of the staff
The installation and maintenance of the system may only be carried out by qualified personnel.
2.2.1. Electrical Specialist Personnel
Skilled electrical personnel include persons who
-
are able to carry out work on electrical systems due to their technical training, knowledge and experience as well as knowledge of the relevant standards and regulations.
-
have been commissioned and trained by the operator to carry out work on electrical systems and equipment of the battery system.
-
are familiar with how the battery system works.
-
recognize hazards and prevent them by taking appropriate protective measures.
2.3. General information on the FENECON Home 10 storage system
-
Assembly of the FENECON Home 10, installation of the battery modules and cable connections as well as expansion of the system may only be carried out by qualified electricians.
-
Keep the power storage system away from children and animals
-
The power storage system may only be used under the specified charging/discharging conditions (see chapter Technical data).
-
Only use the battery modules as intended. Improper use can lead to overheating, explosion or fire of the battery modules.
-
Read the instructions for installation and operation to avoid damage due to incorrect operation.
-
The power storage system can cause electric shock and, due to short-circuit currents, burns.
-
The battery modules may have insufficient cell voltage after a long storage period. If this is the case, please contact the service department.
-
Do not expose the battery modules to high voltages.
-
Place the battery modules on level surfaces.
-
Do not place any objects on the FENECON Home 10 battery tower.
-
Do not step on the power storage system.
-
Do not connect the plug contacts of the BMS box in reverse.
-
Do not short-circuit battery modules.
-
Do not touch the battery module connectors (+) and (-) directly with a wire or metal object (e.g. metal chain, hairpin). In the event of a short circuit, excessive current can be generated, which can lead to overheating, explosion or fire of the battery modules.
2.3.1. Elementary influences
-
Keep the power storage system away from water sources.
-
Do not immerse the power storage system in water, moisten it or touch it with wet hands.
-
Set up/store the electricity storage system in a cool place.
-
Do not heat the electricity storage system.
-
Do not expose the power storage system to naked flames.
-
Do not set up or use the power storage system near naked flames, heaters or high-temperature sources.
-
The heat can cause insulation to melt and the safety ventilation to be damaged. This can lead to overheating, explosion or fire in the battery modules.
-
-
No soldering work may be carried out on the power storage system. Heat introduced during soldering can damage the insulator and the safety ventilation mechanism and lead to overheating, explosion or fire of the battery modules.
-
The battery modules must not be dismantled or modified. The battery modules contain a safety mechanism and a protective device, damage to which can lead to overheating, explosion or fire of the battery modules.
2.3.2. Mechanical influences
-
Do not attempt to crush or open battery modules.
-
Do not apply any mechanical force to the power storage system.
-
The battery modules can be damaged and short circuits can occur, which can lead to overheating, explosion or fire of the battery modules.
-
-
Do not throw or drop parts of the power storage system.
-
Do not use defective or dropped battery modules.
-
-
Do not use the power storage system if changes in color or mechanical damage are detected during Assembly, charging, normal operation and/or storage.
-
If the protective devices are damaged, abnormal charging currents and voltages can cause a chemical reaction in the battery modules, which can lead to overheating, explosion or even fire in the battery modules.
2.3.3. Installation, operation and maintenance
Always observe the following safety instructions when installing, operating or maintaining the battery modules:
-
Assembly of the FENECON Home 10, installation of the battery modules and cable connections as well as expansion of the system may only be carried out by qualified electricians.
-
During maintenance work, stand on dry insulating objects and do not wear any metal objects/jewelry (e.g. watches, rings and necklaces) during maintenance work/operation.
-
Use insulated tools and wear personal protective equipment.
-
Do not touch two charged contacts with a potential difference.
-
Measure the battery voltage with a multimeter and ensure that the output voltage is 0 V in off mode.
-
If an anomaly is detected, switch off the battery tower immediately.
-
Only continue the maintenance work after the causes of the anomaly have been eliminated.
-
The battery modules can cause an electric shock and burns due to high short-circuit currents.
-
Install battery modules in locations with good natural ventilation.
2.4. Reasonably foreseeable misuse
All applications that do not fall within the scope of the intended use are considered misuse. Work on live parts is generally not permitted. Electrical work may only be carried out by qualified electricians.
The following safety rules must be observed for all work on electrical components:
-
Unlock
-
Secure against restarting
-
Determine absence of voltage
-
Earthing and short-circuiting
-
Cover or cordon off neighboring live parts
Non-compliance with the safety rules is considered a reasonably foreseeable misuse.
Other misapplications are in particular:
-
improper transportation, installation or assembly at a location, trial operation or operation which may damage the FENECON Home 10.
-
Changes to the specified performance data, including the individual components.
-
Change or deviation of the specified connected loads.
-
functional or structural changes.
-
Operating the product in a faulty or defective condition.
-
improper repairs.
-
operation without protective devices or defective protective devices.
-
Disregarding the information in the original operating instructions.
-
Unauthorized or unauthorized access via the control unit or the network.
-
Fire, open light and smoking in the vicinity of the storage system.
-
Inadequate ventilation at the installation site.
-
unauthorized changes and actions to the storage system.
-
Use as mobile energy storage.
-
Direct use in a PV system (integration via an AC-coupled Grid is possible).
2.5. Area of application - electromagnetic compatibility (EMC)
The low-voltage equipment is intended for use in the following areas of application:
-
General information (public)
Use in other areas of application is not in accordance with the intended use.
2.5.1. Storage
-
Area: Fireproof indoors/outdoors with suitable weather protection.
-
Air temperature: -20 °C to 40 °C.
-
Relative humidity: max. 50% at +40 °C.
-
Do not store battery modules (lithium iron phosphate batteries) with flammable or toxic objects.
-
Store battery modules with safety defects separately from undamaged battery modules.
2.5.2. Fire protection
-
Do not expose the power storage system to direct sunlight
-
Avoid contact with conductive objects (e.g. wires).
-
Keep heat and fire sources, flammable, explosive and chemical materials away from the power storage system
-
Do not dispose of the FENECON Home 10 battery modules in a fire due to the risk of explosion
2.6. Operating resources
2.6.1. Electrolyte solution of the battery modules
-
Electrolyte solution is used in the battery modules (lithium iron phosphate).
-
The electrolyte solution in the battery modules is a clear liquid and has a characteristic odor of organic solvents.
-
The electrolyte solution is flammable.
-
The electrolyte solution in the battery modules is corrosive.
-
Contact with electrolyte solution can cause severe burns to the skin and damage to the eyes.
-
Do not inhale the vapors.
-
If the electrolyte solution is swallowed, induce vomiting.
-
Leave the contaminated area immediately after inhaling the vapors.
-
Eye and skin contact with leaked electrolyte solution must be avoided.
-
After skin contact: Immediately wash skin thoroughly with neutralizing soap and consult a doctor if skin irritation persists.
-
After eye contact: Immediately flush eye(s) with running water for 15 minutes and seek medical advice. Delayed treatment may cause serious damage to health.
-
3. Technical data
3.1. General information
designation | value/size | |
---|---|---|
Installation / ambient conditions |
IP classification |
IP55 |
Operating altitude above sea level |
≤ 2,000 m |
|
Installation/operating temperature |
-30 °C to +60 °C |
|
Battery operating temperature |
-10 °C to +50 °C |
|
Optimal battery operating temperature |
15 °C to +30 °C |
|
Cooling |
Fanless |
|
Max. Grid connection |
120 A |
|
Certification / Directive |
Overall system |
CE |
Inverter |
VDE 4105:2018-11 |
|
Battery |
UN38.3 |
3.2. Technical data - Inverter
Naming | Value/size | ||
---|---|---|---|
Inverter model |
FHI-10-DAH |
FHI-10-DAH 16A |
|
DC-PV connection |
Max. DC input power |
15 kWp |
15 kWp |
MPP tracker |
2 |
2 |
|
Inputs per MPPT |
1 (MC4) |
1 (MC4) |
|
Starting voltage |
180 V |
180 V |
|
Min. DC feed-in voltage |
210 V |
210 V |
|
Max. DC feed-in voltage |
1000 V |
1000 V |
|
MPPT voltage range |
200 V - 850 V |
200 V - 850 V |
|
MPPT voltage range full load |
460 V - 850 V |
460 V - 850 V |
|
Max. Input current per MPPT |
12.5 A |
16 A |
|
Max. Short-circuit current per MPPT |
15.5 A |
22.7 A |
|
AC connection |
Grid connection |
400/380 V, 3L/N/PE, 50/60 Hz |
400/380 V, 3L/N/PE, 50/60 Hz |
Max. Output current |
16.5 A |
16.5 A |
|
Max. Input current |
22 A |
22 A |
|
Nominal apparent power output |
10,000 VA |
10,000 VA |
|
Max. Apparent power output |
11,000 VA |
11,000 VA |
|
Max. Apparent power from mains |
15,000 VA |
15,000 VA |
|
Cos(φ) |
-0.8 to +0.8 |
-0.8 to +0.8 |
|
Back-up power |
Back-up power capability |
Yes |
Yes |
Grid shape |
400/380 V, 3L/N/PE, 50/60 Hz |
400/380 V, 3L/N/PE, 50/60 Hz |
|
Back-up power supplied Loads (per phase) |
10.000 VA (3,333 VA)* |
10,000 VA (3,333 VA)* |
|
Shift load |
3,333 VA |
3,333 VA |
|
Black start |
Yes |
Yes |
|
Solar Recharging |
Yes |
Yes |
|
Efficiency |
Max. Efficiency |
98.2 % |
98.2 % |
European Efficiency |
97.5 % |
97.5 % |
|
General information |
Width | Depth | Height |
415 | 180 | 516 mm |
415 | 180 | 516 mm |
Weight |
24 kg |
24 kg |
|
Topology |
trafolos |
trafolos |
also in mains parallel operation
3.3. Technical data - FENECON Home 10 - EMS-Box
Naming | Value/Size |
---|---|
Operating voltage DC |
117.6 V - 500 V |
Max. Current (battery) |
40 A |
Max. Voltage (PV) |
1,000 V |
Max. Current (PV) |
12.5 A |
Operating temperature |
-30°C - 60°C |
Protection class |
IP55 (plugged in) |
Input voltage |
100 V - 240 V / 1.8 A / 50 Hz - 60 Hz |
Width | Depth | Height |
506 | 365 | 145 mm |
Weight |
11 kg |
installation |
stackable |
3.3.2. EMS-Box - Pin assignment
Item | Description |
---|---|
1 |
Battery connection to the Inverter (MC4) |
2 |
Interface for future developments |
3 |
Customer network connection (LAN) RJ45 (not included in scope of delivery) |
4 |
Inverter communication, relay outputs; digital inputs |
5 |
Earth connection |
6 |
Communication output for parallel connection of several batteries |
7 |
Power supply e.g. NYM-I 3x1.5 mm2 (not included in scope of delivery) |
3.4. Technical data - FENECON Home 10 - Parallel box (optional)
Naming | Value/Size |
---|---|
Operating voltage DC |
117.6 V - 500 V |
Max. Current (battery) |
40 A |
Operating temperature |
-30°C~60°C |
Protection class |
IP55 (plugged in) |
Width | Depth | Height |
506 | 365 | 145 mm |
Weight |
10 kg |
installation |
stackable |
3.4.2. Parallel box - pin assignment
Item | Description |
---|---|
1 |
Battery connection to the Inverter (MC4) |
2 |
Battery connection from the two other battery towers (MC4) |
3 |
Communication input for parallel connection of several battery towers |
4 |
Earthing connection |
5 |
Communication output for parallel connection of several battery towers |
3.5. Technical data - FENECON Home 10 - Extension box (optional)
Naming | Value/Size |
---|---|
Operating voltage DC |
117.6 - 500 V |
Max. Current (battery) |
40 A |
Operating temperature |
-30°C~60°C |
Protection class |
IP55 (plugged in) |
Width | Depth | Height |
506 | 365 | 145 mm |
Weight |
9 kg |
installation |
stackable |
3.6. Technical data - FENECON Home 10 - BMS-Box
Naming | Value/Size |
---|---|
Maximum operating voltage range |
117.6 V - 500 V |
Maximum output/input current |
40 A |
Optimum operating temperature |
15 to 30 °C |
Ambient temperature range |
-10 to 50 °C |
Protection class |
IP55 (plugged in) |
Width (incl. side cover) | Depth | Height |
506 | 365 | 131 mm |
Weight |
13kg |
installation |
stackable / wall mounting |
3.7. Technical data - FENECON Home 10 - Battery module
Naming | Value/Size |
---|---|
Usable capacity |
49.1 Ah / 2.2 kWh |
Rated voltage |
44.8 V |
Output voltage range |
39.2 V - 50.4 V |
Storage temperature range (over 7 days) |
-30 °C to +60 °C |
Storage temperature range (over 30 days) |
-20 °C to +55 °C |
Storage temperature range (over 180 days) |
-10 °C to +50 °C |
Protection class |
IP55 (plugged in) |
Weight |
26.5 kg |
Installation |
Stackable |
Parallel connection |
3 battery towers in parallel |
Cooling |
natural cooling |
Shipping capacity |
< 30 % SOC |
Module safety certification |
VDE 2510/IEC62619 |
UN transportation test standard |
UN38.3 |
Relative humidity during storage |
5 % to 95 % |
Storage longer than 6 months |
3.7.1. Electrical parameters of the battery modules
For number of battery modules from 4 to 6
Parameter | Value/Size | ||
---|---|---|---|
Number of modules |
4S |
5S |
6S |
Nominal capacity |
8.8 kWh |
11.0 kWh |
13.2 kWh |
Width incl. side cover |
506 mm |
||
Depth |
397 mm |
||
Height (without feet) |
924 mm |
1055 mm |
1186 mm |
Weight |
133.5 kg |
160.0 kg |
186.5 kg |
Rated voltage |
179.2 V |
224 V |
268.8 V |
Output voltage range |
156.8~201.6 V |
196~252 V |
235.2~302.4 V |
Maximum continuous charging/discharging power |
4.48 kW |
5.60 kW |
6.72kW |
With a number of battery modules from 7 to 10
Parameter | Value/Size | |||
---|---|---|---|---|
Module |
7S |
8S |
9S |
10S |
Nominal capacity |
15.4 kWh |
17.6 kWh |
19.8 kWh |
22.0 kWh |
Width incl. side cover |
506 mm |
|||
Depth |
397 mm |
|||
Height (without feet) |
131.7 mm |
1448 mm |
1579 mm |
1710 mm |
Weight |
213.0 kg |
239.5 kg |
266.0 kg |
292.5 kg |
Rated voltage |
313.6 V |
358.4 V |
403.2 V |
448.0 V |
Output voltage range |
274.4~352.8 V |
313.6~403.2 V |
352.8~453.6 V |
392~493 V |
Maximum continuous charging/discharging power |
7.84 kW |
8.96 kW |
10.0 kW |
10.0 kW |
4. General information
FENECON Home 10 is a Back-up power capability Battery energy storage system that can build its own household power grid. Lithium iron phosphate batteries (LiFePO4) are used in this modular system for storing electrical energy.
4.1. System configuration - general overview
4.2. System design variants
4.2.1. Standard setup with Back-up Power
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
Inverter |
5 |
PV system |
6 |
FENECON Home 10 |
7 |
Consumption |
4.2.2. Standard setup with Schuko and Back-up Power
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
Inverter |
5 |
PV system |
6 |
FENECON Home 10 |
7 |
3x Schuko with RCD type A 30 mA and fuse (to be obtained externally from installer) |
8 |
Consumption |
4.2.3. System setup with additional PV generator and Back-up Power
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
3-phase sensor or with PV Inverter App |
5 |
PV Inverter |
6 |
Additional PV system |
7 |
FENECON Home 10 |
8 |
PV system |
9 |
Inverter |
10 |
Consumption |
4.2.4. System design as AC system (and Back-up Power)
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
3-phase sensor or with PV Inverter App |
5 |
PV Inverter |
6 |
PV system |
7 |
FENECON Home 10 |
8 |
Inverter |
9 |
Consumption |
4.2.5. System with manual emergency power changeover
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
Inverter |
5 |
PV system |
6 |
FENECON Home 10 |
7 |
Manual Back-up Power switch |
8 |
Consumption |
4.2.6. System setup with automatic consumer switchover (AVU)
Item | Description |
---|---|
1 |
Grid |
2 |
2 bi-directional meter |
3 |
Smartmeter |
4 |
Automatic load switching (AVU) * |
5 |
Inverter |
6 |
PV system |
7 |
FENECON Home 10 |
8 |
Consumption |
*To install the AVU, use the associated assembly and operating instructions. These can be found on the FENECON website in the download center at: https://fenecon.de/files-avu/.
4.2.7. Required components
Depending on the system configuration, a maximum of the following components are required. When connecting up to three battery towers in parallel, ensure that the same number of battery modules are installed in each battery tower.
Number of battery towers |
Number of battery modules max. |
BMS incl. Base |
FEMS |
||
Box |
Parallel-Box |
Extension-Box |
|||
1 |
10 |
1 |
1 |
- |
- |
2 |
20 |
1 |
1 |
1 |
- |
3 |
30 |
1 |
1 |
1 |
1 |
5. Assembly preparation
5.1. Scope of delivery
5.1.1. FENECON Home 10 - Inverter
illustration | number | designation |
---|---|---|
1 |
FENECON Home 10 - Inverter |
|
1 |
Wall bracket |
|
1 |
Meter with transducer (transducers are already mounted on the meter) |
|
1 |
Communication module |
|
2 |
MC4 connector |
|
2 |
MC4 socket |
|
1 |
Cable lug + screw for earthing |
|
4 |
Screw with dowel |
|
1 |
Cover AC connection |
|
2 |
Screw for earthing and fixing to wall bracket |
|
1 |
Nut, body washer and spring washer for earthing |
5.1.2. FENECON Home 10 - EMS-Box
illustration | number | designation |
---|---|---|
1 |
FENECON Home 10 - EMS-Box |
|
2 |
Pageblank |
|
2 |
Fixing plates |
|
4 |
Screws M4 x 10 |
|
1 |
Harting housing |
|
1 |
Harting socket |
|
1 |
Screw connection M32 |
|
1 |
Multi-hole rubber |
|
1 |
Plug (230 V) |
|
1 |
End bridge |
|
2 |
Network housing |
|
5 |
Blind plug |
|
1 |
Battery cable set 1.5m |
|
1 |
Assembly and service instructions |
|
1 |
Operating instructions (for the end customer) |
5.1.3. FENECON Home 10 - Parallel box (optional)
illustration | number | designation |
---|---|---|
1 |
FENECON Home 10 - Parallel-Box |
|
2 |
Page Fascia |
|
2 |
Fixing plates |
|
8 |
Screws M4 x 10 |
|
1 |
DC cable set 1.2m |
|
1 |
Communication cable parallel connection 1.5m |
5.1.4. FENECON Home 10 - Extension box (optional)
illustration | number | designation |
---|---|---|
1 |
FENECON Home 10 - Extension-Box |
|
2 |
Pageblend |
|
2 |
Fixing plates |
|
8 |
Screws M4 x 10 |
|
1 |
DC cable set 1.2m |
|
1 |
Communication cable 1.5m |
5.1.5. FENECON Home 10 - BMS Box / Base
illustration | number | designation |
---|---|---|
1 |
FENECON Home 10 - BMS-Box |
|
1 |
Base |
|
2 |
Side panel (FENECON Home 10 - BMS-Box) |
|
2 |
Side cladding (Base) |
|
2 |
Wall mounting mounting bracket (FENECON Home 10 - BMS box part) |
|
2 |
Wall mounting mounting bracket (wall part) |
|
4 |
Feet |
|
2 |
Fixing plates |
|
8 |
Screws M4 x 10 |
|
2 |
Screws M6 |
5.2. Tools required
The following tools are required for Assembly of the system components
Image | Designation | Designation | Designation |
---|---|---|---|
pencil |
level |
||
impact drill / cordless screwdriver |
Screwdriver set |
||
Meter stick |
Page cutter |
||
3mm Allen key |
Crew wrench set |
||
Crimping tool |
Multimeter |
6. Assembly
The following components must be installed:
-
Inverter
-
Battery tower with Base, battery modules, BMS-Box, and FENECON Home 10 - EMS-Box
-
Optional:
-
Battery tower with Base, battery modules, BMS box and parallel box
-
-
Optional:
-
Battery tower with Base, battery modules, BMS Box and Extension Box
-
Before installation, carefully check whether the packaging and products are damaged and whether all accessories listed in chapter 5.1 are included in the scope of delivery. If a part is missing or damaged, contact the manufacturer / dealer.
6.1. Assembly Inverter
6.1.1. Safety instructions
Electric shock from live parts |
Electric shock in the absence of overvoltage protection |
Fire and explosion |
Fire and explosion with deeply discharged battery modules |
Toxic substances, gases and dust + |
Arcing due to short-circuit currents |
Destruction of a measuring device due to overvoltage |
Hot surfaces + |
Weight of the Inverter |
Sand, dust and moisture |
Electrostatic charging |
Cleaning agents |
6.1.2. Installation conditions and distances at the installation site
-
The Inverter must be installed protected from direct sunlight, rain and snow.
Installation conditions |
6.1.3. Assembly
To install the FENECON Home 10 inverter on the wall, proceed as follows:
Assembly of the wall bracket
1. To mount the Inverter, drill 8 mm holes for the enclosed dowels according to the specified dimensions |
|
3. Attach the wall bracket to the wall. Dowels and screws are included for this purpose. Always check the condition of the wall to see whether the wall plugs can be used. |
|
4. Hang the Inverter on the wall bracket using the bracket on the back. |
6.2. Assembly battery tower
6.2.1. Safety instructions
Electric shock from live parts + |
Electric shock in the absence of overvoltage protection + |
Fire and explosion + |
Fire and explosion if battery modules are deeply discharged |
Toxic substances, gases and dust + |
Arcing due to short-circuit currents |
Destruction of a measuring device due to overvoltage |
Hot surfaces + |
Weight of the battery modules |
Sand, dust and moisture |
Electrostatic charging |
Cleaning agents |
location |
Installation |
6.2.2. Conditions at the installation site
Indoor or outdoor installation
It is recommended that the FENECON Home 10 battery tower is installed in a well-ventilated room without sources of external heat. However, the battery tower can also be installed outdoors protected from the weather (e.g. garage).
Installation above 2000 m above sea level and in unventilated areas is not permitted.
Also inadmissible places: - with an explosive atmosphere. - Places where flammable or oxidizing substances are stored. - Wet rooms. - Places where salty moisture, ammonia, corrosive vapors or acid can penetrate the system.
The storage system should be inaccessible to children and animals.
6.2.3. Installation conditions and distances at the installation site
-
The battery tower must be installed protected from direct sunlight, rain and snow.
-
In conditions outside the optimum temperature range, the performance of the battery is reduced. (optimum temperature range +15°C to +30°C)
-
Keep a distance of at least 300 mm from a wall and at least 600 mm from another battery tower.
-
Keep a distance of at least 500 mm from a wall at the front.
-
FENECON Home 10 - The battery tower and Inverter should be installed/mounted on top of each other. If there is not enough space above, the battery tower and inverter can also be installed next to each other.
6.2.4. Assembly of battery tower 1 with FENECON Home 10 - EMS box
Proceed as follows to set up the battery tower:
1. The battery tower is installed stackable in front of a wall on a solid and level floor. |
|
3. Mount the feet to the base with a wrench and align the base horizontally using the height-adjustable feet. |
|
5. Place the Base on the feet at the installation site (if necessary, keep a distance of 45 to 65 mm from a wall) |
|
6. Place an FENECON Home 10 battery module on the Base, paying attention to the plug-in bolts and positioning holes. |
A maximum of 10 FENECON Home 10 battery modules can be stacked on one Base. |
8. Install all remaining FENECON Home 10 battery modules in the same way. |
Electric shock |
9. Assemble the two brackets for the wall bracket using the M6 screws. |
|
10. Attach the brackets to the FENECON Home 10 - BMS box using the enclosed M4 screws. |
|
11. Place the FENECON Home 10 - BMS box on the last battery. |
|
15. FENECON Home 10 - Attach the EMS box. |
16. Fasten the mounting rails on both sides of the battery module stack using the M4 screws supplied. |
|
18. Insert the side panels of the Base, the battery modules, the BMS box and the EMS box. |
You will find the assembly instructions for 2 or 3 battery towers in chapter 7.1. |
6.3. Electrical installation
6.3.1. Earthing the inverter and the battery tower
1. The Inverter must be earthed directly to the equipotential bonding bar. |
|
4. The battery tower must be earthed directly to the equipotential bonding rail. |
|
7. Each additional battery tower (parallel box or extension box) must be earthed directly to the equipotential bonding bar. |
The cross-section of the earthing must be at least 10 mm². |
6.3.2. Connection and wiring of the AC circuit
Item | Description |
---|---|
1 |
Bi-directional meter from energy supplier |
2 |
Fuse protection of the Inverter C25 3-pole *1 |
3 |
Consumption fuse (no Back-up Power) with RCD type A and suitable circuit breakers |
4 |
Service switch for switching the emergency power loads to the power grid (recommended) |
5 |
Consumption protected by suitable MCBs and RCD type A 30 mA *2 |
6 |
Consumption - emergency power supply maximum 10 kW / 3.33 kW per phase (also applies in normal operation if Grid available!); no other AC generators permitted |
7 |
Consumption not supplied with emergency power |
8 |
AC supply of the EMS box (if Consumption is connected to the emergency power outlet) |
9 |
Fuse maximum C6 or C10 1-pole |
10 |
Potential equalization busbar |
*In addition, the currently valid national regulations and the specifications of the associated network operator must be complied with.
*2The currently valid national regulations, the specifications of the associated network operator and the manufacturer’s specifications must be observed.
Item | Description |
---|---|
1 |
Emergency power consumers are supplied with emergency power via inverter (normal position) |
2 |
Emergency power consumers are disconnected from the Inverter and Grid |
3 |
Emergency power consumers are supplied from the Grid |
The automatic emergency power switchover is not affected by the maintenance switch. |
Item | Description |
---|---|
1 |
Bi-directional meter from energy supplier |
2 |
Inverter fuse protection C25 3-pole*1 |
3 |
Consumption fuse (no Back-up Power) with RCD type A and suitable circuit breakers |
4 |
Consumption not supplied with emergency power |
5 |
Folding transformer (directly behind utility meter) already pre-installed on energy meter |
6 |
Energy meter |
7 |
Fuse for the Energy Meter (recommended) B6 3-pole |
*In addition, the currently valid national regulations and the specifications of the associated network operator must be complied with
1.Insert the supply cable of the Inverter and the cable for the emergency power outlet into the cable gland. |
2. Strip the cables |
|||
Section |
Description |
Dimensions |
|
1 |
outer diameter |
13 - 18 mm |
|
2 |
length of stripped cable |
20 - 25 mm |
|
3 |
length of stripped conductor |
7 - 9 mm |
|
4 |
Conductor cross-section |
4 - 6 mm |
|
4. If necessary, fit the conductors with suitable ferrules. |
|||
5. Connect the cables to the intended connections (ON-GRID / OFF-GRID). 8. the Inverter must be pre-fused with a C25 circuit breaker. |
|||
9. Fasten the cable gland to the Inverter. |
10.Checking the connection area of the folding transformer. |
The maximum current carrying capacity is 120 A per phase. |
14. Connect the voltage tap to the marked connections on the energy meter. |
17. It is recommended that a maintenance switch be installed for the emergency power outlet. |
A 4-pole maintenance switch is recommended. Care must be taken to ensure that no star point displacement can occur during switching. The correct maintenance switch must be selected by a specialist company, taking into account the conditions on site. |
This does not affect the function of the automatic emergency power switchover. |
6.3.3. AC connection of the FENECON Home 10 - EMS-Box
An external 230V power supply is required to supply the FENECON Home 10 - EMS-Box.
The purpose of this is to avoid loading the empty battery with additional Consumption. This can occur particularly in winter when there is no sunshine or when there is snow on the PV system.
1. Open the plug using a screwdriver. And pull out the inner part to the front. |
|
2. Insert the cable for the power supply. |
3. Strip the cable. |
|
6. Connect the wires to the connections provided |
|
9. Close the plug. |
|
10. If the system is installed with Back-up Power, the AC power supply of the battery tower must be connected on the Back-up Power side. |
6.3.4. DC cable from the battery tower to the Inverter
This chapter can be skipped if there are several battery towers.
You will find the assembly instructions for 2 or 3 battery towers in chapter 7.2. |
1. Use the enclosed 1.5m DC cable to connect the battery tower and Inverter. |
6.3.5. Connection and cabling of PV system
The PV system can be connected directly to the Inverter at the PV inputs. |
Type 2 overvoltage protection is integrated in the inverter. |
6.3.6. Connecting the communication module to the inverter
Connect the communication module to the inverter. (Included with the Inverter) |
If the plug is not plugged in, this can lead to grid detection problems with the Inverter. |
6.3.7. Communication between meter and inverter
The communication cable (network cable) for the Energy Meter is already connected to the inverter. |
6.3.8. Communication between battery and inverter
1. The communication cable for communication with the EMS-Box is already connected to the Inverter. |
|
3. Insert the cable through the gland and the multi-hole rubber into the Harting housing. |
|
4. Connect the white wire to terminal 1. |
Pin 3 is designed as ground for the RS485 connection. This means that other cables with shielding can also be connected. |
If controllable Consumptions have been installed and one of the following FEMS extensions has been purchased, the following two steps can be neglected for the time being. |
7. Then screw the socket into the Harting housing. |
|
10. Connecting the Harting plug to the battery tower. |
6.3.9. Communication from a battery tower
If only one battery tower is installed, the end jumper (included) must be plugged into the PARALLEL OUT connection and locked by turning the underside. |
You will find the assembly instructions for 2 or 3 battery towers in chapter 7.3. |
6.3.10. Communication to customer network
If the battery tower is installed indoors, this point can be skipped. And the network cable can be plugged in directly. |
1. To seal the network connections, insert the cable into the plug and screw it in place. Only the rubber seal and the screw connection are required. |
|
2. Make sure that the network plug protrudes approx. 3 mm over the bayonet catch at the front. |
|
4. For the Internet connection and for the configuration of the storage system, connect the network cable to the LAN port of the battery (yellow), and the other end of the cable to the customer’s network. |
The storage system does not have a W-Lan function. |
6.3.11. Cover for the internal input (optional)
Optionally, a network housing with blind plugs (included in the scope of delivery) can be used as a cover for the internal connection. |
All inputs have a degree of protection of IP55. There is no need to cover unused connections. |
7. Parallel connection of several battery towers
7.1. Assembly of further battery towers
7.1.1. Assembly battery tower two with FENECON Home 10 - parallel box
If a second battery tower is available, the parallel box is attached to the second battery tower instead of the EMS box.
To do this, repeat the steps from chapter 6.2.4. In step 11, attach the FENECON Home 10 parallel box instead of the FENECON Home 10 EMS box. |
7.1.2. Assembly battery tower three with FENECON Home 10 - Extension Box
If a third battery tower is available, the extension box is attached to the third battery tower instead of the EMS box.
To do this, repeat the steps from chapter 6.2.4. In step 11, insert the FENECON Home 10 extension box instead of the FENECON Home 10 EMS box. |
7.2. Electrical installation of additional battery towers
7.2.1. DC cable between two battery towers and the Inverter
1. Use the enclosed 1.5m DC cable to connect the second battery tower to the Inverter. |
|
5. The two battery towers are connected to each other using the cable set supplied in the parallel box. |
7.2.2. DC cable between three battery towers and the Inverter
1. Use the enclosed 1.5m DC cable to connect the battery tower and Inverter. |
|
5. The three battery towers are connected to each other using the cable sets supplied in the parallel box and the extension box. |
7.3. Communication of further battery towers
7.3.1. Communication between two battery towers
1. If two battery towers are operated, the enclosed network cable must be plugged in and locked between tower 1 PARALLEL OUT and tower 2 PARALLEL IN. |
7.3.2. Communication between three battery towers
1. If three battery towers are operated, the enclosed network cables between tower 1 PARALLEL OUT and tower 2 PARALLEL IN and between tower 2 PARALLEL OUT and tower 3 PARALLEL IN must be plugged in and connected between the three towers. |
7.4. Capacity expansion of the battery tower
by one or more battery modules
The battery tower can be stacked up to 10 battery modules to form a battery tower.
If further battery modules are added after the IBN, the following procedure must be followed:
Open the online monitoring. |
|
Click on Storage system in the online monitoring. |
|
In online monitoring under Storage system, activate the "Capacity expansion" function. The "Capacity expansion" is activated when the blue bar is displayed. You can now choose between "Immediate start" and "Planned expansion", with the two options the battery is charged/discharged to 30%. When the charge level is reached, charging/discharging is stopped and the charge level of 30% is maintained. |
|
When you select the "Planned extension", you can select the planned day and the planned time. In this example, 24.05.2024 and the time of 09:00 were selected. At this time, the battery is expected to be charged/discharged to reach 30% for the "Planned extension". |
|
Finally, you must confirm your desired settings by clicking on the blue tick. The desired extension will be saved and, depending on the option selected, executed immediately or later at a specific time. |
The capacity can also be extended at a later date; there is no time limit here. You will not reach the full capacity with the new battery module, as the new module adapts to the old modules.
If the battery tower is extended by additional battery modules after several weeks or months, the following procedure must be followed:
29-30 % SOC |
1 Charge / discharge the system to a charge level of 29-30 %. And then switch off. |
2. Switch off the entire system. The exact procedure is described in detail in chapter 9.2.2. |
|
3. Remove the top three side panels on each side. |
5. Remove the EMS box and BMS box and place them on their sides. To do this, unscrew the wall bracket of the BMS box from the wall. |
|
6. Attach the new battery module. |
|
7. Proceed as described in chapter 6.2.4 from step 8. |
If the exact voltage value of the old and new battery modules has not been matched, SOC jumps will occur when the battery [.SpellE]#is charged and discharged. This means that the full capacity is temporarily not available.
After approx. 20 cycles, the cells should have equalized and there are no more jumps and the capacity is also fully usable.
7.5. Extension of the battery tower by one or more battery towers
Up to three battery towers can be operated in parallel.
The capacity can also be subsequently increased by adding one or two more battery towers of the same capacity; there is no time limit for this. You will not reach the full capacity with the new battery module, as the new module will equalize with the old modules.
If the battery tower is extended by further battery towers after several weeks or months, the following procedure must be followed:
29-30 % SOC |
8. Charge/discharge the system to a charge level of 29-30%. And then switch off. |
9. Switch off the entire system. The exact procedure is described in detail in chapter 9.2.2. |
|
10. Installation of the new battery towers as described in chapter 7.1.1 and chapter 7.1.2. |
|
14. Run the commissioning wizard again. |
If the exact voltage value of the old and new battery towers has not been matched, the new batteries will not be connected.
This is not displayed as an error, but it can happen that the SOC displays of the individual battery towers show different charge levels.
When the charge levels have equalized after a charging cycle, the last battery towers also switch on.
The battery towers work independently, so the flashing frequency of the different towers may vary. The SOC display of the individual towers may also differ briefly.
8. FEMS extensions
The integrated relays can be used directly on the (first) battery tower for the following FEMS extensions. Various pins on the 16-pin connector plug are provided for this purpose. A total of three free relay channels are available.
Not all apps can be connected at the same time.
For further information on the following apps, please visit our homepage.
If the three integrated relays are not sufficient, an external 8-channel relay board can be connected via Ethernet. |
The pin assignment of the Harting connector is shown in detail below. |
Item | Description |
---|---|
1 |
RS485 connection |
2 |
Additional PE |
3 |
Digital inputs DI1-DI4 (currently not available) |
4 |
+12 V DC |
5 |
Relay 1 |
6 |
Relay 2 |
7 |
Relay 3 |
8.1. Connection of a Heat pump via "SG-Ready"
The integration of an "SG-Ready" (Smart Grid-Ready) Heat pump is an advanced form of sector coupling of electricity and heat - often also referred to as a "Power-to-Heat" application. The control system ensures that the Heat pump slightly overheats the thermal storage unit at times when cheap (solar) electricity is available in order to save electrical energy at times when there is no cheap surplus electricity.
1. The internal relay contacts 2 and 3 can be connected via pins 13/14 and 15/16 on the Harting connector. |
8.2. Connection of a Heating element with a maximum of 6 kW
The integration of an electric Heating element is the simplest and cheapest form of sector coupling of electricity and heat - often also called a "power-to-heat" application.
If the capacity of the electrical storage unit is exhausted, self-generated energy must be fed into the public Grid with low remuneration. In these cases, it often makes sense to use the surplus electricity for water heating (e.g. for hot water buffer tanks, pool heating, etc.). In this way, other energy sources (e.g. wood or oil) can be saved.
1. So that each phase of the Heating element can be controlled separately, each phase must be connected individually to a relay. |
Manual mode is only suitable for temporary operation. For permanent operation, the external relay control must be used. |
8.3. Control of a Heating element greater than 6 kW
(control via external relay)
The integration of an electric Heating element is the simplest and cheapest form of sector coupling of electricity and heat - often referred to as a "power-to-heat" application.
When the capacity of the electrical storage unit is exhausted, self-generated energy must be fed into the public Grid at a low rate. In these cases, it often makes sense to use the surplus electricity to heat water (e.g. for hot water buffer storage tanks, pool heating, etc.). In this way, other energy sources (e.g. wood or oil) can be saved. The externally installed relays must be designed according to the installed output of the installed Heating element.
1. So that each phase of the Heating element can be controlled separately, each phase must be connected individually to the internal relay via an additional external relay. |
|
4. As an alternative to L2/L3, L1 can of course also be looped through, or +.
5. Alternatively, control the contactors/relays with 24V. If a different voltage source is used, A2 must not be connected to N. |
|
6. The voltage supply of the Heating element must then be connected to the switching contacts of the relays. If another voltage source is used, A2 must not be connected to N. |
8.4. Control of a CHP unit
The integration of a Combined heat and power plant (CHP) into electrical energy management is an advanced form of sector coupling of electricity and heat.
This makes it possible to utilize the property of the CHP unit as an electrical generator that is independent of the time of day and weather conditions. For example, the CHP unit is given a switch-on signal to produce electricity when the storage unit’s charge level is low. This is useful, for example, if the battery capacity is not sufficient to cover electricity consumption at night. This avoids the need to purchase expensive electricity from the Grid.
When the battery is charging, this signal is stopped again to prevent the CHP unit from feeding electricity into the grid unnecessarily.
1. The enable signal for starting the CHP unit can be connected via pins 11/12. |
8.5. Additional AC meter
If other meters have been installed for monitoring other consumers or generators, these must be integrated into the circuit in accordance with the manufacturer’s instructions.
The communicative integration is shown below using a Socomec Countis E24 as an example.
Only meters approved by the company FENECON can be integrated.
The first generation meter is always integrated with Modbus ID 6. All others in ascending order.
The baud rate must be 9600.
1. Instead of connecting the communication line of the Inverter directly to pin 1/2, as described in chapter 6.3.8, the communication line to the meter must be connected to pin 1/2. |
||
3. The connection to the Inverter is then established from the meter. This means that two wires must be connected to one connection on the meter. |
||
from the battery tower |
white to 3 |
|
brown to 2 |
||
to the Inverter |
white to 3 |
|
orange to 2 |
8.6. §14a EnWG
The Inverter can be limited to a maximum reference power of 4.2 kW. The digital input of the EMS must be assigned for this.
1. The signal can be connected to pins 5 (C) and 8 (A) via the Harting connector (16-pin - A & C). |
9. Initial commissioning
9.1. Checking the installation, connections and cabling
Check the system as follows before initial commissioning:
-
All components (distances, environment, mounting) are installed correctly.
-
All internal wiring is complete and properly connected.
-
All external supply lines (power supply, communication cable) are properly connected.
-
All connected loads are matched to the system and the necessary settings have been made.
-
All necessary tests of the system were carried out in accordance with the standards.
9.2. Switching the system on/off
9.2.1. Switch on
1. fuse the EMS box (sub-distribution board, or socket outlet) |
|
4. securing the battery tower (front battery tower) |
6. When the green LED on the Inverter lights up during back-up, the button on the EMS-Box can be pressed for approx. 5 seconds. |
|
8. When the LED bar starts to flash, the button can be released. |
If the system has not yet been configured, the battery goes into error mode or switches off. |
9.2.2. Switch off
1. securing the battery tower (front battery tower) |
|
3. If present, switch off the PV system with the DC switch on the Inverter. |
|
6. The system is only completely switched off when all LEDs on the Inverter and the battery are no longer lit. This can take approx. 30 seconds. |
9.3. Configuration via commissioning wizard
Open the FENECON homepage and click on the login for FEMS online monitoring "FEMS Login" in the top right-hand corner. Alternatively, you can use the QR code below or the link to access the page.
2. Log in with your installer account. |
|
3. If an installer account has not yet been created, it can be created directly under the login window. |
|
5. Once all the necessary points have been confirmed, the account will be created automatically |
7. First you must enter the 16-digit installer key. |
|
11. After completing the IBN, the system is ready for operation and you will be forwarded directly to live monitoring. |
|
10. FEMS-Online-Monitoring
The FEMS online monitoring is used to visualize all energy flows in your system. The energy monitor shows live data on grid consumption or feed-in, PV production, charging/discharging of the battery storage system and power consumption. Other widgets display the percentage of self-sufficiency and self-consumption. In addition, the individual widgets offer a detailed view, which can also be used to view the performance values with phase accuracy.
In addition to the pure information display, all additionally purchased FEMS extensions, such as for integrating a Heat pump, Heating element, e-charging station or Combined heat and power plant (CHP), are also listed in the online monitoring. Their functionality can be controlled via the corresponding widget.
In addition to the live view, the history offers the option of selecting user-defined time periods for online monitoring. The status of the entire system and the individual components can be monitored at any time using the info icon.
10.1. Access data
Access to FEMS online monitoring is separated according to end customer and installer.
10.2. Installation of further FEMS apps
When you ordered the FEMS app, you received a 16-digit license key. You can use this license key to redeem the app independently in the FEMS App Center.
Open Online Monitoring |
|
Click on the burger menu in the top left corner |
|
Open the "Settings" tab |
|
Now select the "FEMS App Center" button and open it by clicking on the arrow |
|
You have now reached the App Center. Now click on the "Redeem license key" button at the top right |
|
Enter the 16-digit license key in the input field. Then click on Validate. The license key is then checked. |
|
Click on "Redeem license key". You will then receive a selection of apps that can be redeemed with the license key. |
|
Now select the app you want to install. Here, for example, "SolarEdge PV Inverter". |
|
Click on "Install app" and enter the necessary data (e.g. IP address of the PV inverter) in the input mask. |
|
Click on "Install app" to complete the installation |
11. Troubleshooting
11.1. FEMS-Online-Monitoring
The system status can be checked after logging in at the top right using the color of the symbol. A green tick indicates that everything is OK, an orange exclamation mark indicates a warning (Warning) and a red exclamation mark indicates an error (Fault).
11.1.1. Fault display
System status: Everything is OK |
|
System status: Warning |
|
System status: Error (Fault) |
11.1.2. Troubleshooting
For a detailed overview of an existing warning or error, click on the exclamation mark in the top right-hand corner. |
|
The scroll bar can be used to examine the origin of the warning or error in more detail. |
|
Clicking on the symbol (down arrow) displays a more detailed error description depending on the error. |
In the example above, an incorrect reference for the network counter was intentionally entered for test purposes, which is why the controller fails to run.
Under certain circumstances it can happen that the FEMS is not accessible and the adjacent error message appears. |
If the FEMS is offline, follow the steps displayed below the message.
11.2. FENECON Home 10 - Inverter
11.2.1. Fault display
Faults are indicated on the Inverter via the LED display [FAULT] as follows:
Rotary field of the Grid connection
-
Check whether a clockwise rotating field is present at the Grid connection.
-
Otherwise, contact the FENECON service. The contact details can be found in chapter 11.5.
The LEDs display further information on the status of the Inverter.
11.3. Battery tower
11.3.1. Fault display
Faults are displayed on the FENECON Home 10 BMS box via a red LED.
The various faults are indicated by LED codes.
Storage unit status |
Storage unit information |
LEDs |
|||||
blue/red |
1 |
2 |
3 |
4 |
|||
Boot loader |
|||||||
Start |
Master / Slave |
||||||
Parallel Box |
|||||||
Extension Box |
|||||||
Test mode |
Single or parallel connection |
||||||
SOC Display |
|||||||
Charging |
0%-25.0% SOC |
||||||
25.1%-50.0% SOC |
|||||||
50.1%-75.0% SOC |
|||||||
75.1%-99.9% SOC |
|||||||
100% SOC |
|||||||
Discharge and standby |
100%-75.1% |
||||||
75.0%-50.1% |
|||||||
50.0%-25.1% |
|||||||
25.0%-0% |
|||||||
error |
Overvoltage |
||||||
undervoltage |
|||||||
overtemperature |
|||||||
undertemperature |
|||||||
Overcurrent |
|||||||
SOH too low |
|||||||
Int. communication |
|||||||
Ext. communication |
|||||||
Address error Parallel |
|||||||
Address error modules |
|||||||
BMS box backup |
|||||||
Module backup |
|||||||
contact error |
|||||||
isolation error |
|||||||
BMS error |
Blue permanently on |
|
blinking blue |
|
Blue flashing quickly |
|
Red permanently on |
11.4. Fault list
Component | Disturbance | Measure |
---|---|---|
Battery module |
The battery module has become wet |
Do not touch |
Battery module |
The battery module is damaged |
A damaged battery module is dangerous and must be handled with the utmost care. |
11.5. Service
The FENECON service must be contacted in the event of system faults:
Phone: +49 (0) 991 64 88 00 33
E-Mail: service@fenecon.de
Our service hours:
Mon. - Thurs. 8 - 12 | 13 - 17 o’clock
Fri. 8 - 12 | 13 - 15 o’clock
12. Technical maintenance
12.1. Tests and inspections
When carrying out inspection work, ensure that the product is in a safe condition. Improperly performed inspections can have serious consequences for people, the environment and the product itself. |
Inspection work may only be carried out by trained and qualified specialists. |
The maintenance instructions of the component manufacturer must be observed for all individual components. |
Check the product and the cables regularly for visible external damage. If components are defective, contact FENECON service. Repairs may only be carried out by a qualified electrician.
12.2. Cleaning
Cleaning agents: The use of cleaning agents can damage the Battery energy storage unit and its parts.
It is recommended that the Battery energy storage unit and all its parts are only cleaned with a cloth moistened with clean water.
The entire product must be cleaned regularly. Only suitable cleaning agents may be used for this purpose. |
14. Dismantling and disposal
14.2. Waste disposal
-
The FENECON Home 10 must not be disposed of with normal household waste.
-
The FENECON Home 10 is RoHS and REACH compliant.
-
Disposal of the product must comply with local regulations for disposal.
-
Avoid exposing the battery modules to high temperatures or direct sunlight.
-
Avoid exposing the battery modules to high humidity or corrosive atmospheres.
-
Dispose of the storage system and the batteries it contains in an environmentally friendly manner.
-
Do not dispose of the FENECON Home 10 battery modules in a fire due to the risk of explosion.
-
Contact FENECON GmbH to dispose of the used batteries.