FENECON Home 20 & 30 Assembly and Operating Instructions:

1. Version/revision

Table 1. Version/revision

Version/Revision

Change

Date

Name

2023.10.1

First draft

09/10/2023

FENECON TK

2023.11.1

Addition of sections 10-17

16/11/2023

FENECON TK

2023.12.1

Fault rectification

05/12/2023

FENECON TK

2024.01.1

Fault rectification/extension of section 11

10/01/2024

FENECON TK

2024.04.1

Fault rectification/extension of section 11.2

19/04/2024

FENECON TK

2024.07.1

Adaptation of section 10

15/07/2024

FENECON PM

2024.10.1

Adaptation section 11

02/10/2024

FENECON MR

2024.11.1

Adaptation of section 9

05/11/2024

FENECON MR

2025.1.1

Integration of fire department notice

27/01/2025

FENECON MR

2025.8.1

Integration split base

01/08/2025

FENECON TK/MR

2025.11.1

Integration flood warning

03/11/2025

FENECON PM

2. Symbol conventions

Table 2. Symbol conventions
This symbol indicates an imminent danger. If this danger is not avoided, it can lead to death or serious injury.
This symbol indicates a potentially dangerous situation. If this dangerous situation is not avoided, it may result in minor or moderate injury.
This symbol indicates a warning. Failure to observe this warning may result in damage and/or destruction of the system.
This symbol indicates a note. It is recommended that the note be observed.

3. Structure of warning notices

Warning notices protect against possible personal injury and damage to property if observed and classify the magnitude of the danger by means of the signal word.

Source of the danger
Possible consequences of non-compliance

  • Measures for avoidance/prohibitions

Danger sign
The danger sign indicates warnings that warn of personal injury.

Source of danger
The source of danger indicates the cause of the hazard.

Possible consequences of non-compliance
The possible consequences of ignoring the warning are e. g. crushing, burns or other serious injuries.

Measures/prohibitions
Measures/prohibitions include actions that must be taken to avoid a hazard (e. g. stop the drive) or that are prohibited to avoid a hazard.

4. Terms and abbreviations

The following terms and abbreviations are used in the installation and service instructions:

Table 3. Terms and abbreviations
Term/abbreviation Meaning

AC

Alternating Current

CHP

Combined heat and power plant (CHP)

BMS

Battery Management System

DC

Direct Current

EMS

Energy Management System

Energy meter

Electricity meter for the inverter at the grid connection point

FEMS

FENECON Energy Management System

Commissioning

Commissioning

MPPT

Maximum Power Point Tracking Finder for the maximum power point

GCP

grid connection point

PE

Protective conductor

PV

Photovoltaics

RTE

Round-Trip-Efficiency (RTE)
System efficiency — ratio of discharged to charged energy quantity

SG-Ready

Smart-Grid-Ready — Preparation of the heat pump for external control

SoC

State of Charge
State of charge The available capacity in a battery, expressed as a percentage of the nominal capacity.

SoH

State of Health — State of ageing

VDE

German Association for Electrical, Electronic & Information Technologies e. V.

Widget

Component of Online Monitoring

5. Scope of delivery

Table 4. Scope of delivery
Item Component Number Comment

1

FENECON Home 20 & 30-Inverter

1

Depending on version, 20 or 30 kW

2

FENECON Home 20 & 30-EMS Box (incl. FENECON Energy Management System )

1

3

FENECON Home 20 & 30-Parallel Box

1

optional for 2nd FENECON Home 20 & 30 battery tower

4

FENECON Home 20 & 30-Extension Box

1

optional for 3rd & 4th FENECON Home 20 & 30 battery tower

5

FENECON Home 20 & 30-BMS Box

1

each FENECON Home 20 & 30-Battery Tower

6

FENECON Home 20 & 30-Battery module

depending on the capacity ordered

7

FENECON Home 20 & 30-Base

1

per FENECON Home 20 & 30-battery tower

Table 5. Documents
Component Comment

Operating instructions FENECON Home 20 & 30

Instructions for the installer

Quick start guide FENECON Home 20 & 30

Quick start guide for the installer

Operating instructions FENECON Home 20 & 30

Instructions for the user/end customer

Brochure FENECON Home 20 & 30

6. Applicable documents

All documents in the appendix of these installation and service instructions need to be observed. Cf. 15.1 Additional documents

7. Availability

The operator must keep these installation and service instructions or relevant parts of them within easy reach in the immediate vicinity of the product.

If the product is handed over to another person, the operator passes these installation and service instructions on to that person.

8. Safety

8.1. Intended use

The FENECON electrical energy storage system is used to store electrical energy in rechargeable lithium iron phosphate battery modules (charging) and to provide electrical energy (discharging). This charging and discharging process takes place via a connected inverter. The system must only be used in compliance with the permissible technical data (see section Technical data).

FENECON power storage systems consist of various modules. In particular, these include a BMS (battery management system), the FENECON Energy Management System (FEMS), battery modules and bases. All processes of the electricity storage system are monitored and controlled by the FEMS.

Any other use is not an intended use.

8.2. Reasonably foreseeable misuse

All applications that do not fall within the scope of the intended use are considered misuse.

Work on live parts is generally not permitted. Electrical work must only be carried out by qualified electricians.

The following safety rules must be observed for all work on electrical components:

  1. Disconnect.

  2. Secure against restarting.

  3. Check that there is no voltage.

  4. Earth and short-circuit.

  5. Cover or shield neighboring live parts.

Non-compliance with the safety rules is considered a reasonably foreseeable misuse.

Other misuses include in particular:

  • improper transportation, installation or assembly at a location, trial operation or operation that could damage the system.

  • change in the specified technical characteristics, including the individual components.

  • change or deviation of the connected load.

  • functional or structural changes.

  • operating the product in a faulty or defective condition.

  • improper repairs.

  • operation without protective devices or with defective protective devices.

  • disregarding the information in the original installation and service instructions.

  • unauthorized access via the control unit or the network.

  • the installation of firmware updates that were not obtained via FENECON.

  • fire, open light and smoking in the vicinity of the storage system.

  • insufficient ventilation at the installation site.

  • unauthorized changes and actions to the electrical energy storage system.

  • use as mobile energy storage.

  • direct use in a PV system (integration via an AC-coupled grid is possible).

8.3. Area of application — Electromagnetic compatibility (EMC)

The low-voltage equipment is intended for use in the following areas of application:

  • General public (public)

Use in other areas of application is not in accordance with the intended use.

8.4. Qualification of the staff

Qualified personnel must be deployed for the intended use, installation and maintenance of the system. The area of responsibility, competence and supervision of the personnel must be precisely regulated by the operator.

8.4.1. Trained electricians

Trained electricians include persons who:

  1. are able to carry out work on electrical systems due to their technical training, knowledge and experience as well as knowledge of the relevant standards and regulations.

  2. have been commissioned and trained by the operator to carry out work on electrical systems and equipment of the battery system.

  3. are familiar with how the battery system works.

  4. recognize hazards and prevent them by taking appropriate protective measures.

8.4.2. Service staff

Service personnel includes the manufacturer’s personnel or specialist personnel instructed and authorized by FENECON GmbH, who must be requested by the operator to work on the system (e. g. assembly, repair, maintenance, work on the batteries, etc.).

8.5. General information on the FENECON system

The product must be positioned in such a way that sufficient room for movement can be guaranteed for service and maintenance personnel in every phase of the product’s life. The service life of the product depends on the service life and maintenance intervals carried out by qualified personnel. The service life is particularly influenced by preventive maintenance and servicing.

  • The battery modules must only be installed and the cable connections made by trained electricians.

  • The electrical energy storage system must only be used under the specified charging/discharging conditions (see section Technical data).

  • Keep the electrical energy storage system away from children and animals.

  • Do not connect the plug contacts of the BMS box in reverse.

  • Do not short-circuit battery modules.

  • Only use the battery modules as intended.

    • Improper use can lead to overheating, explosion or fire of the battery modules.

  • Read the instructions for installation and operation to avoid damage due to incorrect operation.

  • The battery modules may have insufficient cell voltage after a long storage period. If this is the case, please contact the service department

  • Do not expose the battery modules to high voltages.

  • Place the battery modules on level surfaces.

  • Do not place any objects on the FENECON battery towers.

8.5.1. Environmental influences

  • Keep the electrical energy storage system away from water sources.

  • Do not immerse the electrical energy storage system in water, moisten it or touch it with wet hands.

  • Set up/store the electrical energy storage system in a cool place.

  • Do not heat the electrical energy storage system.

  • Do not expose the electrical energy storage system to open fire.

  • Do not set up or use the electrical energy storage system near open fires, heaters or high-temperature sources.

    • The heat can cause insulation to melt and the safety ventilation to be damaged. This can lead to overheating, explosion or fire on the battery modules.

  • No soldering work must be carried out on the electrical energy storage system. Heat introduced during soldering can damage the insulator and the safety venting mechanism and lead to overheating, explosion or fire of the battery modules.

8.5.2. Mechanical influences

  • The battery modules must not be dismantled or modified. The battery modules contain a safety mechanism and a protective device, damage to which can lead to overheating, explosion or fire of the battery modules.

  • Do not step on the electrical energy storage system.

  • Do not attempt to crush or open battery modules.

  • Do not apply any mechanical force to the electrical energy storage system.

    • The battery modules can be damaged and short circuits can occur, which can lead to overheating, explosion or fire of the battery modules.

  • Do not throw or drop parts of the power storage system.

    • Do not use defective or dropped battery modules.

  • Do not use the electrical energy storage system if changes in color or mechanical damage are detected during assembly, charging, normal operation and/or storage.

  • If the protective devices are damaged, abnormal charging currents and voltages can cause a chemical reaction in the battery modules, which can lead to overheating, explosion or even fire in the battery modules.

8.5.3. Installation, operation and maintenance

When carrying out maintenance, servicing and cleaning work, ensure that the product is switched off in a safe manner and secured against being switched on again. In addition, all instructions in these installation and service instructions must be followed.

Always observe the following safety instructions when installing, operating or maintaining the battery modules:

  • Installation/maintenance work and making cable connections must only be carried out by qualified personnel (trained electricians).

  • During maintenance work, stand on dry insulating objects and do not wear any metal objects (e.g. watches, rings and necklaces) during maintenance work/operation.

  • Use insulated tools and wear personal protective equipment.

  • Do not touch two charged contacts with a potential difference.

  • Measure the battery voltage with a multimeter and ensure that the output voltage is 0 V in off mode.

  • If an anomaly is detected, switch off the battery tower immediately.

  • Only continue the maintenance work after the causes of the anomaly have been eliminated.

  • The battery modules can cause electric shock and burns due to high short-circuit currents.

  • Do not touch the battery module connectors (+) and (-) directly with a wire or metal object (e. g. metal chain, hairpin). Excessive current can be generated in the event of a short circuit, which can lead to overheating, explosion or fire of the battery modules.

8.5.4. Fire protection

  • Do not expose the electrical energy storage system to direct sunlight.

  • Avoid contact with conductive objects (e. g. wires).

  • Keep heat and fire sources, flammable, explosive and chemical materials away from the electrical energy storage system.

  • Explosion hazard: Do not dispose of battery modules in a fire!

8.5.5. Storage

  • Area: Fireproof indoors/outdoors with suitable weather protection.

  • Air temperature: -20 °C to 40 °C.

  • Relative humidity: max. 50 % at +40 °C.

  • Do not store battery modules (lithium iron phosphate batteries) with flammable or toxic objects.

  • Store battery modules with safety defects separately from undamaged battery modules.

Storage longer than 12 months
Possible consequences: Deep discharge of the cells/defective battery.

  • External charging of the battery modules to nominal voltage — forced charging must be carried out, which is controlled via the FEMS. This must only be carried out by the manufacturer or by a company commissioned by the manufacturer.

8.5.6. Charging

  • Keep the SoC of the battery module below 30% for shipping and charge the battery module if it has been stored for more than 12 months.

8.6. Operating resources

8.6.1. Electrolyte solution of the battery modules

  • Electrolyte solution is used in the battery modules (lithium iron phosphate).

  • The electrolyte solution in the battery modules is a clear liquid and has a characteristic odor of organic solvents.

  • The electrolyte solution is flammable.

  • The electrolyte solution in the battery modules is corrosive.

  • Do not inhale the vapors.

  • If the electrolyte solution is swallowed, induce vomiting.

  • Leave the contaminated area immediately after inhaling the vapors.

  • Eye and skin contact with leaked electrolyte solution must be avoided.

  • Contact with electrolyte solution can cause severe burns to the skin and damage to the eyes.

    • After skin contact: Immediately wash skin thoroughly with neutralizing soap and consult a doctor if skin irritation persists.

    • After eye contact: Immediately flush eye(s) with running water for 15 minutes and seek medical advice.

Delayed treatment can cause serious damage to health.

8.7. Residual risk

Warning of electrical voltage

Work on electrical equipment may only be carried out by qualified electricians from the manufacturer or by specially authorized, trained electricians and in compliance with the safety regulations.
Maintenance work must not be carried out for 5 minutes after the power supply has been disconnected.
The customer must provide a mains disconnection device for the electrical power supply.

Unknown fault messages

Unknown faults and attempts to rectify them can lead to damage to the product.
If there is a fault that is not included in the fault list, inform customer service.

All doors, emergency exits and areas around the electrical energy storage system must remain clear; do not obstruct escape routes!

The condition of the floor outside the storage system is the responsibility of the user. However, the housing is sealed so that no electrolyte can escape.

8.8. Behavior in emergency situations

Proceed as follows in emergency situations:

  1. Disconnect the electrical energy storage system from the grid.

  2. Leave the zone of danger immediately.

  3. Secure the area.

  4. Inform those responsible.

  5. Call a doctor if necessary.

8.9. Pictograms

Pictograms on the system indicate dangers, prohibitions and instructions. Illegible or missing pictograms must be replaced by new ones.

Table 6. Pictograms
Pictogram Meaning Description
W012

Warning of dangerous electrical voltage

Pictogram on the enclosure, and marking of components which do not clearly indicate that they contain electrical equipment which may be the cause of a risk of electric shock.

W001

General warning sign

W026

Battery charging hazard warning

Pictogram on enclosure and marking of components not clearly identified as containing electrical equipment that may give rise to a battery charging hazard.

P003

No naked flames; fire, naked source of ignition and smoking prohibited

Pictogram on the enclosure and marking of components that do not clearly indicate that they contain electrical equipment that may present a risk of naked flames, fire, naked sources of ignition and smoking.

grounding

Protective earthing symbol

electro bin

Separate collection of electrical and electronic equipment

M002

Note instructions

M014

Use protective headgear

M008

Use protective footwear

M009

Use protective gloves

CE logo

CE mark

recycle

Product is recyclable.

8.10. Operating materials/equipment

8.10.1. Electrolyte solution of the battery modules

  • Electrolyte solution is used in the battery modules (lithium iron phosphate).

  • The electrolyte solution in the battery modules is a clear liquid and has a characteristic odor of organic solvents.

  • The electrolyte solution is flammable.

  • The electrolyte solution in the battery modules is corrosive.

  • Contact with electrolyte solution can cause severe burns to the skin and damage to the eyes.

  • Do not inhale the vapors.

  • If the electrolyte solution is swallowed, induce vomiting.

  • Leave the contaminated area immediately after inhaling the vapors.

  • Eye and skin contact with leaked electrolyte solution must be avoided.

    • After skin contact: Immediately wash skin thoroughly with neutralizing soap and consult a doctor if skin irritation persists.

    • After eye contact: Immediately flush eye(s) with running water for 15 minutes and seek medical advice.

Delayed treatment can cause serious damage to health.

8.10.2. Electrical equipment

  • Work on electrical equipment must only be carried out by qualified electricians.

  • The five safety rules must be observed for all work on electrical components:

    1. Disconnect.

    2. Secure against restarting.

    3. Check that there is no voltage.

    4. Earth and short-circuit.

    5. Cover or shield neighboring live parts.

  • Maintenance work must only be carried out by trained specialist personnel (service personnel).

  • Before starting work, carry out visual checks for insulation and housing damage.

  • The system must never be operated with faulty or non-operational electrical connections.

  • To avoid damage, lay supply lines without crushing and shearing points.

  • Only insulated tools must be used for maintenance on uninsulated conductors and terminals.

  • Control cabinets (e. g. inverter housing) must always be kept locked. Only authorized personnel with appropriate training and safety instructions (e. g. service personnel) should be allowed access.

  • The inspection and maintenance intervals for electrical components specified by the manufacturer must be observed.

  • To avoid damage, lay supply lines without crushing and shearing points

  • If the power supply is disconnected, specially marked external circuits may still be live!

  • Some equipment (e. g. inverters) with an electrical intermediate circuit may still carry dangerous residual voltages for a certain period of time after disconnection. Before starting work on these systems, check that they are de-energized.

8.11. Personal protective equipment

Depending on the work on the system, personal protective equipment must be worn:

  • Protective footwear

  • Protective gloves, cut-resistant if necessary

  • Protective eyewear

  • Protective headgear

8.12. Spare and wear parts

The use of spare and wear parts from third-party manufacturers can lead to risks. Only original parts or spare and wear parts approved by the manufacturer must be used. The instructions for spare parts must be observed. Further information can be found in the wiring diagram.

Further information must be requested from the manufacturer.

8.13. IT security

FENECON systems and their applications communicate and operate without an internet connection. The individual system components (inverters, batteries, etc.) are not directly connected to the internet or accessible from the Internet. Sensitive communications via the internet are processed exclusively via certificate-based TLS encryption.

Access to the programming levels is not barrier-free and is accessible at different levels depending on the qualifications of the operating personnel. Safety-relevant program changes require additional verification.

FENECON processes energy data of European customers exclusively on servers in Germany and these are subject to the data protection regulations applicable in this country.

The software used is checked using automated tools and processes established during development in order to keep it up to date and to rectify security-relevant vulnerabilities at short notice. Updates for FEMS are provided free of charge for life.

9. Technical data

9.1. General

Table 7. Technical data — General
designation value/size

Installation/environmental conditions

IP classification

IP55

Operating altitude above sea level

≤ 2,000 m

Installation/operating temperature

-30 °C to +60 °C

Relative humidity (operation/storage)

50 % non-condensing (up to 90 % permissible for short periods)

Battery operating temperature

-10 °C to +50 °C

Optimal operating temperature of the battery

15 °C to +30 °C

Cooling

adaptive fan

Loudness

< 45 dB

Max. Grid connection

120 A

Certification/guideline

Overall system

CE

Inverter

VDE 4105:2018-11
Gate generator type A 1.1

Battery

UN38.3
VDE 2510-50

9.2. Technical data — Inverter

Table 8. Technical data — Inverter
Description Value/dimension

Inverter model

FHI-20-DAH

FHI-30-DAH

DC PV connection

Max. DC input power

30 kWp

45 kWp

MPP tracker

2

3

Number of inputs per MPPT

2 (MC4)

2 (MC4)

Starting voltage

200 V

200 V

Max. DC operating voltage in V

950 V

950 V

Max. DC input voltage in V

1000 V

1000 V

MPPT voltage range

200 V to 850 V

200 V to 850 V

Nominal input voltage in V

620 V

620 V

Max. Input current per MPPT

30 A

30 A

Max. short-circuit current per MPPT

38 A

38 A

AC connection

Grid connection

400/380 V, 3L/N/PE, 50/60 Hz

400/380 V, 3L/N/PE, 50/60 Hz

Max. output current

29 A

43.3 A

Max. input current

45 A

50 A

Nominal apparent power output

20,000 VA

29,900 VA

Max. apparent power output

22,000 VA

29,900 VA

Max. apparent power from the grid

30,000 VA

33,000 VA

Cos(φ)

-0.8 to +0.8

-0.8 to +0.8

Emergency power

Emergency power capable

Yes

Yes

Network configuration

400/380 V, 3L/N/PE, 50/60 Hz

400/380 V, 3L/N/PE, 50/60 Hz

Emergency power supplied with emergency power (per phase)

20.000 VA (6,666 VA)*

29,900 VA (9,966 VA)*

Unbalanced load

6,666 VA

9,999 VA

Black start

Yes

Yes

Solar recharging

Yes

Yes

Efficiency

Max. Efficiency

98.0 %

98.0 %

European efficiency

97.5 %

97.5 %

General

Width | Depth | Height

520 | 220 | 660 mm

520 | 220 | 660 mm

Weight

48 kg

54 kg

Topology

not insulated

not insulated

*also in parallel mains operation

9.2.1. Dimensions

The dimensions are given in mm.

inverter dimensions 20 30
Illustration 1. Inverter — Dimensions

9.3. Technical data — FENECON Home 20 & 30-EMS-Box

Table 9. Technical data — FENECON Home 20 & 30-EMS-Box
Naming Value/Size

Operating voltage DC

224 V to 672 V

Max. Current (battery)

50 A

Operating temperature

-10 °C to 50 °C

Protection class

IP55 (plugged in)

Input voltage

100 V to 240 V/1.8 A/50 Hz to 60 Hz

width | depth | height

506 | 401 | 157 mm

Weight

12 kg

installation

stackable

9.3.1. Dimensions

The dimensions are given in mm.

EMS dimensions
Illustration 2. Dimensions — EMS box

9.3.2. EMS box — Pin assignment

EMS terminals 20 30
Illustration 3. Terminal assignment — EMS box
Table 10. Terminal assignment — EMS box
Item Description

1

Battery connection to the Inverter (MC4-Evo stor)

2

Communication output for parallel connection of several batteries

3

Customer network connection (LAN) RJ45 (network cable not included)

4

Communication Inverter, relay outputs; digital inputs (16-pin connector)

5

Power supply FEMS box; potential-free contacts (max. 10 A, measured) (10-pin plug)

6

Earth connection

7

For future applications (not assigned)

9.4. Technical data — FENECON Home 20 & 30 Parallel box (optional)

Table 11. Technical data — Parallel box
Naming Value/Size

Operating voltage DC

224 V to 672 V

Max. Current (battery)

50 A

Operating temperature

-10 °C ~ 50 °C

Protection class

IP55 (plugged in)

Width | Depth | Height

506 | 401 | 157 mm

Weight

10 kg

installation

stackable

9.4.1. Dimensions

The dimensions are given in mm.

parallelswitchbox dimensions 20 30
Illustration 4. Dimensions — Parallel box

9.4.2. Parallel box — Terminal assignment

parallelswitchbox terminals 20 30
Illustration 5. Terminal assignment — Parallel box
Table 12. Terminal assignment — Parallel box
Item Description

1

Battery connection to the Inverter (MC4-Evo stor)

2

Communication output for parallel connection of several battery towers

3

Communication input for parallel connection of several battery towers

4

Battery connection for additional battery towers (MC4-Evo-stor)

5

Earthing connection

9.5. Technical data — FENECON Home 20 & 30 extension box (optional)

Table 13. Extension box (optional) — Technical data
Naming Value/Size

Operating voltage DC

224 V to 672 V

Max. Current (battery)

50 A

Operating temperature

-10 °C ~ 50 °C

Protection class

IP55 (plugged in)

Width | Depth | Height

506 | 401 | 157 mm

Weight

9 kg

installation

stackable

9.5.1. Dimensions

The dimensions are given in mm.

ExtBox dimensions 20 30
Illustration 6. Dimensions — Extension box

9.5.2. Extension box — Terminal assignment

ExtBox terminals 20 30
Illustration 7. Pin assignment — Extension box
Table 14. Pin assignment — Extension box
Item Description

1

Battery connection to EMS box in parallel (MC4-Evo stor)

2

Communication output for parallel connection of several battery towers

3

Communication input for parallel connection of several battery towers

4

Earthing connection

9.6. Technical data — FENECON Home 20 & 30-BMS-Box

Table 15. Technical data — BMS box
Description Value/Size

Maximum operating voltage range

224 V to 672 V

Maximum output/input current

50 A

Optimum operating temperature

15 to 30 °C

Operating temperature range

-20 to 55 °C

Protection class

IP55 (plugged in)

Width (incl. side panel) | Depth | Height

506 | 401 | 143 mm

Weight

13 kg

Installation

stackable/wall mounting

9.6.1. Dimensions

The dimensions are given in mm.

BMS dimensions 20 30
Illustration 8. Dimensions — BMS box

9.7. Technical data — FENECON Home 20 & 30 battery module

Table 16. Technical data — Battery module
Naming Value/Size

Usable capacity

62.4 Ah/2.80 kWh

Rated voltage

44.8 V

Output voltage range

39.2 V to 50.4 V

Battery operating temperature range

-20 °C to +55 °C

Storage temperature range (over 7 days)

-30 °C to +60 °C

Storage temperature range (over 30 days)

-20 °C to +55 °C

Storage temperature range (cumulative up to 270 days)

-10 °C to +45 °C

Protection class

IP55 (plugged in)

Weight

30 kg

Installation

Stackable

Parallel connection

4 battery towers in parallel

Cooling

natural cooling

Shipping capacity

< 30 % SOC

Module safety certification

VDE 2510/IEC62619

UN transportation test standard

UN38.3

Relative humidity during storage

5 % to 95 %

Storage longer than 12 months
Possible consequences: Deep discharge of the cells Defect of the battery module.
- External charging of the battery modules to nominal voltage. This must only be carried out by the manufacturer or a company commissioned by the manufacturer.

9.7.1. Electrical parameters of the battery modules

For battery modules 5 to 7

Table 17. Electrical parameters — Number of battery modules 4S to 6S (5 to 7 modules in series)
Parameter Value/size

Number of modules

5S

6S

7S

Nominal capacity

14.0 kWh

16.8 kWh

19.6 kWh

Width incl. side panel

506 mm

Depth

401 mm

Height

1120 mm

1263 mm

1406 mm

Weight

187 kg

217 kg

247 kg

Nominal voltage

224.0 V

268.8 V

313,6 V

Output voltage range

196 V ~ 252 V

235.2 V ~ 302.4 V

274.4 V ~ 352.8 V

Maximum continuous charging/discharging power

11.20 kW

13.44 kW

15.68 kW

For battery modules 8 to 11

Table 18. Electrical parameters — Number of battery modules 7S to 10S (8 to 11 modules in series)
Parameter Value/Size

Module

8S

9S

10S

11S

Nominal capacity

22.4 kWh

25.2 kWh

28.0 kWh

30.8 kWh

Width incl. side panel

506 mm

Depth

401 mm

Height

1549 mm

1692 mm

1835 mm

1978 mm

Weight

277 kg

307 kg

3370 kg

367 kg

Rated voltage

358.4 V

403.2 V

448.0 V

492.8 V

Output voltage range

313.6 V ~ 403.2 V

352.8 V ~ 453.6 V

392.0 V ~ 504.0 V

431.2 V ~ 554.4 V

Maximum continuous charging/discharging power

17.92 kW

20.16 kW

22.40 kW

24.64 kW

For battery modules 12 to 15

Table 19. Electrical parameters — Amount of battery modules 7S to 10S (12 to 15 modules in series)
Parameter Value/Size

Module

12S

13S

14S

15S

Nominal capacity

33.6 kWh

36.4 kWh

39.2 kWh

42.0 kWh

Width incl. side panel

506 mm

Depth

401 mm

Height

2121 mm

2264 mm

2407 mm

2550 mm

Weight

397 kg

427 kg

457 kg

487 kg

Rated voltage

537.6 V

582.4 V

627.2 V

672.0 V

Output voltage range

470.4 V ~ 604.8 V

509.6 V ~ 655.2 V

548.8 V ~ 705.6 V

588.0 V ~ 756.0 V

Maximum continuous charging/discharging power

26.88 kW

29.12 kW

30.00 kW

30.00 kW

9.8. Technical data — Base

Table 20. Technical data — Base
Designation Value/dimension

Width (incl. side panel) | Depth | Height

506 | 401 | 84 mm

Weight

6 kg

Protection specification

IP55 (plugged in)

Installation

stackable

9.8.1. Dimensions — Base

The dimensions are given in mm.

base dimensions
Illustration 9. Dimensions — Base

9.9. Technical data — Split base (optional)

Table 21. Technical data — Split base
Designation Value/dimension

Width (incl. side panel) | Depth | Height

1312 | 401 | 84 mm

Weight

11 kg

Protection specification

IP55 (plugged in)

Installation

stackable

9.9.1. Dimensions — Split base

The dimensions are given in mm.

split base dimensions
Illustration 10. Dimensions — Split base

9.10. Technical data — Top box (with option: split base)

Table 22. Technical data — Top box
Description Value/dimension

Width (incl. side panel) | Depth | Height

506 | 401 | 157 mm

Weight

9 kg

Protection specification

IP55 (plugged in)

Installation

stackable

9.10.1. Dimensions — Top box

The dimensions are given in mm.

split base top box
Illustration 11. Dimensions — Top box

10. General description

The FENECON Home 20 & 30 is a Back-up power capability Battery energy storage system that can build its own household power grid. Lithium iron phosphate batteries (LiFePO4) are used in this modular system for storing electrical energy.

10.1. System configuration — General overview

system config optional 20 30
Illustration 12. System — Schematic diagram with optional components (shown without protective device)

10.2. System structure: Variants with emergency power

10.2.1. Standard setup with emergency power

image0013
Illustration 13. Standard setup with emergency power (shown without protective device)
Table 23. Standard setup with emergency power
Item Description

1

Grid

2

2 bi-directional meter

3

Smart meter

4

Inverter

5

PV system

6

FENECON Home 20 & 30

7

Consumption (emergency power supply)

8

Consumption (not supplied with emergency power)

Within the emergency power function, the Inverter acts as its own grid creator and sets up its own 3-phase system for the separate emergency power branch (see Technical data). Compared to the public grid system, the Grid shape of the emergency power mode has a lower "buffer effect" with regard to load peaks, starting currents, DC components and strongly fluctuating Loads. Due to the limited power of the Inverter, such loads are only possible within certain limits.

10.2.2. System structure with additional PV generator

image0015
Illustration 14. System structure with an additional PV generator (shown without protective device)
Table 24. System structure with additional PV generator
Item Description

1

Grid

2

2 bi-directional meter

3

Smart meter

4

3-phase sensor or with PV inverter app

5

PV Inverter

6

Additional PV system

7

FENECON Home 20 & 30

8

PV system

9

Inverter

10

Consumption (not supplied with emergency power)

11

Consumption (emergency power supply)

10.2.3. System structure as an AC system

image0016
Illustration 15. System structure as AC system (shown without protective device)
Table 25. System structure as an AC system
Item Description

1

Grid

2

2 bi-directional meter

3

Smart meter

4

3-phase sensor or with PV inverter app

5

PV Inverter

6

PV system

7

FENECON Home 20 & 30

8

Inverter

9

Consumption (emergency power supply)

10

Consumption (not supplied with emergency power)

10.2.4. System with manual emergency power changeover

image00017
Illustration 16. System with manual emergency power switchover (shown without protective device)
Table 26. System with manual emergency power changeover
Item Description

1

Grid

2

2 bi-directional meter

3

Smart meter

4

Inverter

5

PV system

6

FENECON Home 20 & 30

7

Manual Back-up Power switch

8

Consumption (emergency power supply)

10.2.5. Required components

Depending on the system configuration, a maximum of the following components is required. When connecting up to four battery towers in parallel, ensure that the same number of battery modules is installed in each battery tower.

Table 27. System configuration — Required components

Number of battery towers

Number of battery modules max.

BMS box
(per tower)

EMS box

Parallel box

Extension box

1

15

1

1

-

-

2

30

1

1

1

-

3

45

1

1

1

1

4

60

1

1

1

2

20 30 tower setup
Illustration 17. Structure FENECON Home 20 & 30 storage system with four battery towers

11. Installation preparation

11.1. Scope of delivery

11.1.1. FENECON Home 20 & 30 inverter

Table 28. Scope of delivery — FENECON Home 20 & 30-Inverter
Image Amount Description Item no.
inverter

1

FENECON Home 20 & 30-Inverter

FEH030 and FEH031

wallmount

1

Wall mount

FEH057

image021

1

Meter with transformer (transformers are already mounted on the meter)

FH0055

image022

1

Cover — communication connection

FEH060

MC4 plug

4(6)

MC4 plug

Part of complete set
FEH055

MC4 socket

4(6)

MC4 socket

Part of complete set
FEH055

cable two rtj45

1

Energy meter cable

cable one rtj45

1

FEMS cable

Part of complete set
FEH055

washer nut

20

Nuts for AC connection

Part of complete set
FEH055

image024 4

1

Insulator plate for AC connections

Part of complete set
FEH055

cable lug

10

Cable lugs — AC cable

Part of complete set
FEH055

image026

1

Pin terminal, 3-pin

Part of complete set
FEH055.^

1

Pin terminal, 6-pin

Part of complete set
FEH055

1

Pin terminal, 7-pin

Part of complete set
FEH055

image027

1

Cover — AC connection

FEH056

lens head bolt

2

Bolt for earthing and fixing to wall bracket

Part of complete set
FEH055

11.1.2. FENECON Home 20 & 30-EMS-Box

Table 29. Scope of delivery — FENECON Home 20 & 30-EMS-Box
Image Amount Description Item no.
EMS box

1

FENECON Home 20 & 30-EMS box

FEH013

side panel

2

side panel

Part of complete set
FEH050

image033

2

Harting housing with cable gland (13-21 mm), multi-hole seal (4 x 8 mm)
Harting housing with cable gland (19-25 mm), multi-hole seal (2 x 10 & 1 x 8 mm)

Part of complete set
FEH050

image034

1

Harting socket, 10-pin

Part of complete set
FEH050

image034 1

1

Harting insert 16-pin (assembled)

Part of complete set
FEH050

jumper plug

1

Jumper plug

Part of complete set
FEH050

network cable housing

2

Network connector housing

Part of complete set
FEH050

filler plug 8

5

Filler plug, 8 mm

Part of complete set
FEH050

filler plug 10

2

Filler plug, 10 mm

Part of complete set
FEH050

bat cable

1

Battery cable set, 3 m

Part of complete set
FEH050

installation service manual

1

Installation and service instructions (for the installer)

operating manual

1

Quick start guide (for the installer)

operating manual

1

Operating instructions (for the end customer)

11.1.3. FENECON Home 20 & 30 Parallel box (optional)

Table 30. Scope of delivery — Parallel box
Image Amount Description Item no.
image044

1

FENECON Home 20 & 30 Parallel box

FEH011

side panel

2

side panel

Part of complete set
FEH059

bat cable

2

Two DC cables per set, 2 m

Part of complete set
FEH059

image046

1

Communication cable — parallel connection, 2 m

Part of complete set
FEH059

11.1.4. FENECON Home 20 & 30 extension box (optional)

Table 31. Scope of delivery — Extension box
Image Amount Description Item no.
image047

1

FENECON Home 20 & 30-Extension box

FEH012

side panel

2

Side panel

Part of complete set
FEH059

bat cable

2

two DC cables per set, 2 m

Part of complete set
FEH059

image046

1

communication cable, 2 m

Part of complete set
FEH059

11.1.5. FENECON Home 20 & 30-BMS-Box/Base

Table 32. Scope of delivery — BMS box/base
Image Amount Description Item no.
image050

1

FENECON Home 20 & 30-BMS box

FEH000

image051

1

Base

side panel

2

Side panel (FENECON Home 20 & 30-BMS box)

FEH051

base side panel

2

Side panel (base)

image053

4

Wall mounting — Mounting bracket

Part of connection set
FEH052

image054

4

Wall mounting — Mounting bracket (wall part)

Part of connection set
FEH052

cylinder bolt washer

8

Bolt M4 x 10

Part of connection set
FEH052

bolts m6

2

Bolt for wall mounting M6 x 12

Part of connection set
FEH052

11.1.6. BMS-Box/Splitsockel (optional)

Table 33. Lieferumfang — BMS-Box/Splitsockel (optional)
Abbildung Anzahl Bezeichnung
image050

1

BMS-Box für Splitsockel

top box for split base ISO

1

Abschlussbox für Splitsockel

split base ISO

1

Splitsockel

side panel

4

Seitenblende (BMS-Box)

base side panel

2

Seitenblende (Splitsockel)

image053

4

Wandbefestigung — Befestigungswinkel

image054

4

Wandbefestigung — Befestigungswinkel (Wand-Teil)

cylinder bolt washer

4

Schrauben, M4 x 10

cylinder bolt washer

2

Schrauben für Wandbefestigung, M6 x 12

11.1.7. FENECON Home 20 & 30 battery module

Table 34. Scope of delivery — Battery module
Image Amount Description Item no.
image056

1

Battery module

FEH020

side panel

2

Side panel

FEH051

fixing plate

2

Fixing plates

Part of connection set
FEH053

cylinder bolt washer

2

Bolt M4 x 10

Part of connection set
FEH053

11.2. Tools required

The following tools are required for assembly of the system components:

Table 35. Tools required
Image Description Image Description
pencil

Pencil

spirit level

Spirit level

power drill

Impact drill or
cordless screwdriver

screw drivers

Screwdriver set

folding rule

Meter stick

side cutter

Side cutter

allen key

Allen key, 3 mm

flat spanner

Set of flat spanners

crimping tool

Crimping tool

multimeter

Multimeter

gripping pliers

Pliers for cable glands

protective eyewear photo

Protective eyewear

protective footwear

Safety footwear

dust mask photo

Dust mask

rubber mallet

Rubber mallet

vacuum cleaner

Vacuum cleaner

wire stripper

Wire stripper

protective gloves

Protective gloves

torque wrench

Torque wrench

stripping knife

Stripping knife

12. Installation

  • Do not damage any cables and make sure that nobody steps on the cables or plugs! Damage can lead to serious malfunction!

  • If cables are fed in from the front, the customer must use suitable covers to protect the cables against the risk of tripping.

  • Ensure that all devices in the same network and the battery modules are integrated into the existing surge protection.

  • When drilling holes, avoid water pipes and cables laid in the wall.

  • Wear protective eyewear and a dust mask to prevent dust from being inhaled or getting into your eyes when drilling holes.

  • Make sure that the inverter is securely installed in case it falls down.

  • The DC switch lock of a suitable size should be prepared by the customer. The diameter of the lock is 5 mm. The lock may not be installed if the size is not appropriate.
    Please refer to the supply documentation of the inverter.

Suitable protective covers must be fitted!
All local accident prevention regulations must be observed.

The following components must be installed:

  • Inverter

  • Battery tower with Base, battery modules, BMS-Box, and FENECON Home 20 & 30-EMS-Box

  • Optional:

    • Battery tower with base, battery modules, BMS box and Parallel box

  • Optional:

    • Battery tower with base, battery modules, BMS box and Extension box

Before installation, carefully check whether the packaging and products are damaged and whether all accessories listed in the Scope of delivery are included. If a part is missing or damaged, contact the manufacturer/dealer.

12.1. Assembly — Inverter

12.1.1. Safety instructions

Electric shock from live parts
Death or serious injury to the body and limbs from electric shock when touching live DC cables connected to the electrical energy storage system.

  • Before starting work, de-energize the inverter, the BMS box and the battery modules and secure them against being switched on again.

  • Wait at least 5 minutes after switching off before starting work on the inverter.

  • Observe the safety instructions of FENECON GmbH in the Safety section.

  • Do not touch any exposed live parts or cables.

  • Do not pull the terminal strip with connected DC conductors out of the slot under consumer load.

  • Wear suitable personal protective equipment for all work.

Electric shock in the absence of overvoltage protection
Death or serious injury to the body and limbs from electric shock due to overvoltage (e. g. lightning strike) transmitted via the network cables or other data cables into the building and to other connected devices in the same network due to a lack of overvoltage protection.

  • Ensure that all devices in the same network and the battery modules are integrated into the existing surge protection

  • When laying network cables or other data cables outdoors, ensure that suitable overvoltage protection is in place when the cables from the Inverter or battery tower (battery modules) pass from the outdoor area into a building.

  • The Inverter’s Ethernet interface is classified as "TNV-1" and offers protection against overvoltages of up to 1.5 kV.

Fire and explosion
Death or serious injury to body and limbs due to fire or explosion; in the event of a fault, an ignitable gas mixture may be produced inside the inverter. Switching operations in this condition can cause a fire inside the product or tripped an explosion.

  • In the event of an error, do not carry out any direct actions on the electrical energy storage system.

  • Ensure that unauthorized persons do not have access to the system.

  • Disconnect the battery modules from the Inverter via the DC fuse on the battery tower.

  • Switch off the AC circuit breaker or, if it has already tripped, leave it switched off and secure it against being switched on again.

  • Only carry out work on the inverter (e.g. troubleshooting, repair work) with personal protective equipment for handling hazardous substances (e.g. protective gloves, eye and face protection and respiratory protection).

Fire and explosion with deeply discharged battery modules
Death or serious injury to body and limbs from fire or explosion due to incorrect charging of deeply discharged battery modules

  • Before commissioning the system, ensure that the battery modules are not deeply discharged.

  • Do not operate the system if the battery modules are deeply discharged.

  • If the battery modules are deeply discharged, contact Service

  • Only charge deeply discharged battery modules as instructed by the Service.

Toxic substances, gases and dusts
Damage to electronic components can result in toxic substances, gases and dusts inside the inverter. Touching toxic substances and inhaling toxic gases and dusts can cause skin irritation, chemical burns, breathing difficulties and nausea.

  • Only carry out work on the inverter (e.g. troubleshooting, repair work) with personal protective equipment for handling hazardous substances (e.g. protective gloves, eye and face protection and respiratory protection).

  • Ensure that unauthorized persons do not have access to the inverter.

Arcs due to short-circuit currents
Death or serious injury to the body and limbs due to burns caused by heat development and electric arcs due to short-circuit currents from the battery modules.

  • Before carrying out any work on the battery modules, disconnect the battery modules from the power supply.

  • Observe all safety instructions of the battery manufacturer.

Destruction of a measuring device due to overvoltage
Death or serious injury to the body and limbs due to electric shock when touching a live meter housing: An overvoltage can damage a meter and cause voltage to be applied to the meter housing.

  • Only use measuring devices with a DC input voltage range of at least 600 V or higher.

Hot surfaces
Injuries to the body and limbs due to burning on hot surfaces: The surface of the inverter can become very hot.

  • Mount the inverter in such a way that it cannot be touched accidentally.

  • Do not touch hot surfaces.

  • Before starting work, wait 30 minutes until the surface has cooled down sufficiently.

  • Observe the warning notices on the inverter.

Weight of the inverter
Injuries to the body and limbs due to crushing when falling during transportation or installation of the inverter

  • Transport and lift the Inverter carefully.

  • Note the weight of the Inverter and its center of gravity

  • Wear suitable personal protective equipment when working on the inverter.

Sand, dust and moisture
Ingress of sand, dust and moisture can damage the inverter and impair its function.

Electrostatic charge
Touching electronic components can damage or destroy the inverter via electrostatic discharge.

  • Ground yourself before touching a component.

Cleaning agents
The use of cleaning agents can damage the inverter and/or its parts.

  • Only clean the inverter and all its parts with a cloth moistened with clean water.

12.1.2. Installation conditions and distances at the installation site

installation conditions
Illustration 18. Installation conditions
  • The inverter must be installed protected from direct sunlight, rain and snow.

image077
Illustration 19. Recommended distances at the installation site

Installation conditions

  • The wall must be stable enough for mounting the Inverter and must not be flammable.

  • Maintain a distance of at least 300 mm above the Inverter.

  • Keep a distance of at least 500 mm below the Inverter (cable ducts are not measured here).

  • Keep a distance of at least 300 mm from the front of the Inverter.

  • Laterally: Keep a distance of at least 200 mm to the left of the Inverter and at least 1000 mm to the right.

  • The maximum distance between the Inverter and the installation location of the meter should be based on the cable supplied (10 m). The cable between the meter and the Inverter can be extended up to 100 m.

  • The pre-installed current transformers must not be shortened or extended.

12.1.3. Installation

To install the FENECON Home 20 & 30 inverter on the wall, proceed as follows:

Assembly of the wall bracket

wallmount dimensions
  1. Mark and drill the holes for the wall bracket (Ø 8 mm, depth 80 mm).

  2. Observe minimum clearances.

wallmount montage
  1. Mount the wall bracket on the wall. Always check the condition of the wall to see whether the screw anchors can be used.

wallmount mount
  1. Hook the inverter into the wall mount at the top and bottom using the handles.

wallmount fix
  1. Then secure on the right-hand side using the enclosed screw.

12.2. Assembly of battery tower 1 with FEMS box

12.2.1. Safety instructions

Electric shock from live parts
Death or serious injury to the body and limbs from electric shock when touching live DC cables connected to the electrical energy storage system.

  • Before starting work, disconnect the Inverter, the BMS-Box and the battery modules from the power supply and secure them against being switched on again.

  • Wait at least 5 minutes after switching off before starting work on the inverter.

  • Observe all the manufacturer’s safety instructions in section 2 Safety.

  • Do not touch any exposed live parts or cables.

  • Do not pull the terminal strip with connected DC conductors out of the slot under load.

  • Wear suitable personal protective equipment for all work.

Electric shock in the absence of overvoltage protection
Death or serious injury to the body and limbs from electric shock due to overvoltage (e. g. lightning strike) transmitted via the network cables or other data cables into the building and to other connected devices in the same network due to a lack of overvoltage protection.

  • Ensure that all devices in the same network and the battery modules are integrated into the existing surge protection.

  • When laying network cables or other data cables outdoors, ensure that suitable overvoltage protection is in place when the cables from the inverter or battery tower (battery modules) pass from the outdoor area into a building.

  • The Inverter’s Ethernet interface is classified as "TNV-1" and offers protection against overvoltages of up to 1.5 kV.

Fire and explosion
Death or serious injury to the body and limbs due to fire or explosion; in the event of a fault, an ignitable gas mixture may be produced inside the battery module. Switching operations in this condition can cause a fire inside the product or tripped an explosion.

  • In the event of an error, do not carry out any direct actions on the electrical energy storage system.

  • Ensure that unauthorized persons do not have access to the electrical energy storage system.

  • Disconnect the battery modules from the inverter using an external disconnecting device.

  • Switch off the AC miniature circuit breaker or, if it has already tripped, leave it switched off and secure it against being switched on again.

  • Only carry out work on the inverter (e.g. troubleshooting, repair work) with personal protective equipment for handling hazardous substances (e.g. protective gloves, eye and face protection and respiratory protection).

Fire and explosion with deeply discharged battery modules
Death or serious injury to the body and limbs due to electric shock when touching a live meter housing: An overvoltage can damage a meter and lead to a voltage being applied to the meter housing.

  • Before commissioning the system, ensure that the battery modules are not deeply discharged.

  • Do not operate the system if the battery modules are deeply discharged.

  • If the battery modules are deeply discharged, contact Service.

  • Only charge deeply discharged battery modules as instructed by the Service.

Toxic substances, gases and dusts
Damage to electronic components can result in toxic substances, gases and dusts inside the inverter. Touching toxic substances and inhaling toxic gases and dusts can cause skin irritation, chemical burns, breathing difficulties and nausea.

  • Only carry out work on the inverter (e.g. troubleshooting, repair work) with personal protective equipment for handling hazardous substances (e.g. protective gloves, eye and face protection and respiratory protection).

  • Ensure that unauthorized persons do not have access to the inverter.

Arcs due to short-circuit currents
Death or serious injury to the body and limbs due to burns, heat development and electric arcs due to short-circuit currents from the battery modules.

  • Before carrying out any work on the battery modules, de-energize the battery modules.

  • Observe all safety instructions of the battery manufacturer.

Destruction of a measuring device due to overvoltage
Death or serious injury to the body and limbs due to electric shock when touching a live housing of a measuring device. Overvoltage can damage a measuring device and lead to voltage being applied to the housing of the measuring device.

  • Only use measuring devices with a DC input voltage range of at least 600 V or higher.

Hot surfaces
Injuries to the body and limbs due to burning on hot surfaces: The surface of the inverter can become very hot.

  • Mount the inverter in such a way that it cannot be touched accidentally.

  • Do not touch hot surfaces.

  • Before starting work, wait 30 minutes until the surface has cooled down sufficiently.

  • Observe the warning notices on the inverter.

Weight of the battery modules
Injuries to the body and limbs due to crushing if dropped during transportation or installation of the battery modules.

  • Carefully transport and lift the battery modules.

  • Note the weight of the battery modules and its center of gravity.

  • Wear suitable personal protective equipment for all work on the battery modules.

Sand, dust and moisture
Ingress of sand, dust and moisture can damage the inverter and impair its function.

  • Only set up the battery tower where the humidity is within the limit values and the environment is free of sand and dust.

Electrostatic charging
Touching electronic components can damage or destroy the battery tower via electrostatic discharge.

  • Ground yourself before touching a component.

Cleaning agents
The use of cleaning agents can damage the inverter and/or its parts.

  • Clean the battery tower and all parts of the inverter exclusively with a damp cloth moistened with clear water.

Installation site

  • It is recommended to install the battery tower indoors.

  • If installed outdoors, weather protection (sun and precipitation protection) must be provided.

  • Avoid dirt and dust during assembly.

  • Do not install the battery tower in an area that is at risk of flooding.

  • Do not install the battery tower in very damp areas (e. g. bathrooms).

  • Do not install the battery tower where the ambient conditions are outside the permissible values (section Technical data).

  • Keep the battery tower away from heat sources and fire.

  • Ensure direct contact between the battery module housing and the ambient air and do not cover or shield the battery module.

Installation

  • Wear protective eyewear, insulating gloves and protective footwear when installing the battery modules.

  • Remove all conductive jewelry (e.g. watches, bracelets, rings).

12.2.2. Conditions at the installation site

Indoor or outdoor installation
We recommend installing the FENECON Home 20 & 30 battery tower indoors. However, the battery tower can also be installed outdoors protected from the weather (e.g. garage).

12.2.3. Installation conditions and distances at the installation site

installation conditions
Illustration 20. Installation conditions.
  • The battery tower must be installed protected from direct sunlight, rain and snow.

  • In conditions outside the optimum temperature range, the performance of the battery is reduced. (optional temperature range +15 °C to +30 °C)

battery distances
Illustration 21. Spacing at the installation site
  • A lateral clearance of 300 mm from a wall and 300 mm between two battery towers is recommended.

  • Clearances of 300 mm from a wall are recommended at the front.

  • The FENECON Home 20 & 30 battery tower and Inverter should be installed/mounted one above the other. If there is not enough space above, the battery tower and inverter can also be installed next to each other.

  • A distance of 200 mm from the ceiling is recommended.

If the recommended distances are not observed, installation may be more difficult and derating may occur earlier.

12.2.4. Assembly of battery tower 1 with FENECON Home 20 & 30 EMS box

Proceed as follows to set up the battery tower:

image089
  1. The battery tower is installed stackable in front of a wall on a solid and level floor.

  2. The clearance to the wall must be 40 to 65 mm so that the wall bracket can be fitted correctly.

image090
  1. Place the base on the feet at the installation location (maintain a clearance of 40 to 65 mm from a wall).

image091
  1. Place an FENECON Home 20 & 30 battery module on the base, paying attention to the plug-in bolts and positioning holes.

  2. A black protective film may be stuck to the electrical connectors of the battery. If present, remove this before plugging together.

A maximum of 15 FENECON Home 20 & 30 battery modules can be stacked on one Base.

tower mount battery
  1. Mount all remaining FENECON Home 20 & 30 battery modules in the same way.
    Between 5 and 15 battery modules can be stacked.

Electric shock
Death or serious injury to the body and limbs due to electric shock.

  • Ensure that the circuit breaker of the BMS box is switched off before installing the BMS box.

tower mount bms
  1. Place the FENECON Home 20 & 30 BMS box on the last battery.

tower mount ems
  1. Attach FENECON Home 20 & 30 EMS box.

t mount
  1. Mount the T-piece and the bracket with the enclosed M6 bolt.

tower mount rails
  1. Hook in the mounting rails of the EMS box (wall side) and mark the holes for the wall bracket on the wall (see previous picture).

  2. Drill the holes and screw the wall bracket to the wall.

  3. Hook in all other rails alternately left/right one module lower and screw on with the enclosed bolts.

  4. The following bracket arrangement is recommended for attaching the battery towers.
    From 10 battery modules, two holders must be used on each side.

tower mount side panels
  1. Insert the side panels of the base, the battery modules, the BMS box and the EMS box.

arrangement 5 to 15
Illustration 22. Arrangement of the module fastening

You will find the assembly instructions for 2 or 3 battery towers in the section [Assembly of additional battery towers].

12.3. Installation — Battery tower on split base

The split base can only be used with battery modules with item number FEH021.

The split base is used for a larger footprint installation of a battery tower, which reduces its height and enables installation in rooms with low ceilings.

Proceed as follows to set up a battery tower with a split base:

split base wall distance 2
  1. The battery tower is installed stackable in front of a wall on a solid and level floor.

  2. The clearance to the wall must be 40 to 65 mm so that the wall bracket can be fitted correctly.

split base wall distance 3
  1. Place the base on the feet at the installation location (maintain a clearance of 40 to 65 mm from a wall).

split base first module
  1. Place a battery module on the base, paying attention to the plug-in bolts and positioning holes.

  2. A black protective film may be stuck to the electrical connectors of the battery. If present, remove this before plugging together.

  • A maximum of 15 battery modules can be mounted on one split base.

  • Ensure that the modules are evenly distributed on both sides of the split base.

  • The difference in tower height must not exceed 5 modules.
    → If this cannot be complied with, a maximum of 10 battery modules must be stacked on one side of the system.

split base battery installation
  1. Install all remaining battery modules in the same way.

Electric shock
Death or serious injury to the body and limbs due to electric shock.

  • Ensure that the circuit breaker of the BMS box is switched off before installing the BMS box.

split base bms installation
  1. Place the FENECON BMS box on the last battery.
    It does not matter which of the two towers on the split base the FENECON BMS box is placed on.

split base ems box installation
  1. Attach the FENECON EMS box to the BMS box.

split base top box installation
  1. Place the Top box on the second tower.

extension box top
  1. Place the FENECON extension box on the top of all other split sockets.

bracket connection
  1. Fit the T-piece and the bracket with the enclosed M6 bolt.

split base bracket installation
  1. Hook in the fixing rails of the EMS box and the Top box (wall side) and mark the holes for the wall bracket on the wall.

  2. Drill the holes and screw the wall bracket to the wall.

  3. Hook in all other rails alternately left/right one module lower and fasten with the enclosed bolts.

  4. The arrangement of the mounting brackets shown here is recommended for attaching the battery towers.

See graphic Arrangement of module mounting — Split base for installation details.
split base side panels
  1. Attach the side panels of the split base, the battery modules, the BMS box, the EMS box and the Top box.

split base fixing brackets configuration
Illustration 23. Module mounting arrangement — Split base

12.4. Electrical installation

12.4.1. Earthing the inverter and the battery tower

WR grounding
  1. The inverter must be grounded directly to the earth circuit connector.

  2. Use at minimum a 10 mm2 grounding cable.

  3. To do this, attach the grounding cable to the inverter at the bottom right using the enclosed screw (red).

battery earth 20 30
  1. The battery tower must be grounded directly to the earth circuit connector.

  2. Use at minimum a 10 mm2 grounding cable.

  3. To do this, attach the grounding cable of the EMS box to the grounding bolt (red).

parallel ext earth 20 30
  1. Each additional battery tower (Parallel box or Extension box) must be grounded directly to the earth circuit connector.

  2. Use at minimum a 10 mm2 grounding cable.

  3. To do this, attach the grounding cable of the parallel or extension box to the grounding bolt (red).

The cross-section of the earthing must be at least 10 mm2.
The inverter and the battery towers must be individually grounded to the equipotential bonding.

12.5. Approved network configurations for connecting the FENECON Home 20 & 30

image103
Illustration 24. Approved network configurations for connecting the FENECON Home 20 & 30

12.5.1. Connection and wiring of the AC circuit

setup ac home 20 30
Illustration 25. General information AC connection
Table 36. Components for AC connection (not included in the scope of delivery)
List item Description

1

Bi-directional meter from energy supplier

2

3-pole inverter fuse protection (20 kW — 40 A; 29.9 kW — 63 A)*1

3

Fuse protection of the consumer loads (no emergency power) with RCD type A and suitable MCBs

4

Service switch for switching the emergency power loads to the mains (recommended)

5

Consumer loads protected by suitable MCBs and RCD type A 30 mA *2

6

Consumer loads — supplied with emergency power maximum 20/30 kW/6.666/9.97 kW per phase (also applies in normal operation if grid is available!); no other AC generators permitted

7

Consumer load not supplied with emergency power

8

AC supply to the EMS box (if consumer loads are connected to the emergency power outlet)

9

Fuse protection maximum C6 or C10 1-pole

10

Earth circuit connector

*1 In addition, the currently valid national regulations and the specifications of the relevant grid operator must be observed. (If an RCD is required by the grid operator, an RCD type A with a tripping current of 300 mA is recommended; at 30 mA, unwanted shutdowns may occur.)

*2The currently valid national regulations, the specifications of the associated network operator and the manufacturer’s specifications must be observed.

image00105
image00105 1
Illustration 26. Recommended maintenance switch for emergency power outlet
Table 37. Description of the switch positions of the maintenance switch (not included in the scope of delivery)
List item Description

1

Emergency power consumers are supplied with emergency power via inverter (normal position)

2

Emergency power consumers are disconnected from the inverter and grid

3

Emergency power consumers are supplied from the grid

The automatic emergency power switchover is not affected by the maintenance switch.

AC energymeter diagram
Illustration 27. AC connection Energy meter
Table 38. Components for AC connection
Item Description

1

2 bi-directional meter from energy supplier

2

Inverter fuse protection C40/C63 3-pole*1

3

Consumption fuse (no Back-up Power) with RCD type A and suitable circuit breakers

4

Consumption not supplied with emergency power

5

Folding transformer (directly behind utility meter) already pre-installed on the energy meter

6

Energy meter

7

Fuse for the Energy Meter (recommended) B6 3-pole

*1 In addition, the currently valid national regulations and the specifications of the relevant grid operator must be observed. (If an RCD is required by the grid operator, an RCD type A with a tripping current of 300 mA is recommended; at 30 mA, unwanted shutdowns may occur.)

AC cable w cover 20 30
  1. Insert the inverter supply cable and the cable for the emergency power outlet into the cable gland.

stripping cable
  1. Strip the sheath and the cores.

  2. Make sure that the PE is slightly longer than the other cores.

Section

Description

Dimensions

1

Outer diameter

21 to 26 mm

2

Length of stripped cable

70 to 80 mm

3

Length of stripped conductor

11 to 13 mm

4

Conductor cross-section

10 to 16 mm2

AC cable w cover ferrules 20 30
  1. Press the enclosed cable lugs onto the cores. Alternatively, use other suitable cable lugs. The screw diameter of 5 mm must be observed here.

H20 inverter bottom marked
  1. Connect the cables to the connections provided (ON-GRID/OFF-GRID). To do this, use the nuts provided and tighten to 2-3 Nm.

  2. Ensure that a clockwise rotating field is connected.

  3. Ensure that phase L1 on the inverter and on the energy meter is the same phase; also ensure that this is the case for phases L2 and L3.

  4. The inverter must be pre-fused with a C40/63 MCB.

H20 inverter w cable iso
  1. Fasten the cable gland to the inverter. Tighten the bolts with 3 to 4 Nm.

folding converter
  1. Check the junction box of the split-core CTs.

  2. Connect the transformer in the sub-distribution board directly behind the grid operator’s meter.

  3. To do this, fold the respective transformer around the phases L1 — L3 and close until the lock audibly engages.

  4. The cable between the transformer and the energy meter must not be shortened or extended.

The maximum current carrying capacity is 120 A per phase.
K — from the sub-distribution board
L — to the grid operator’s meter (grid connection)
The cable between the transformer and the energy meter must not be shortened or extended.
The inside diameter of the hinged cable is 16 mm.
The transformer and meter cannot be replaced by other types.
It must be ensured that phase L1 is also phase L1 on the inverter.

image100
  1. Connect the voltage tap to the marked connections on the energy meter.

  2. Pre-fuse the energy meter with a B6A breaker for each phase.

  3. The split-core CTs are already connected. If the measuring sensors of the smart meter were unscrewed during installation for installation reasons, please ensure that they are reconnected in the correct order.

image101
  1. It is recommended that a maintenance switch is installed for the emergency power outlet.

  2. In the event of maintenance or failure of the inverter, the emergency power consumers can continue to be supplied via the power grid.

A 4-pole maintenance switch is recommended. Care must be taken to ensure that no neutral displacement can occur during switching. The correct maintenance switch must be selected by a specialist company, taking into account the conditions on site.

This does not affect the function of the automatic emergency power switchover.

12.5.2. Synchronize to the grid

Table 39. Synchronize to the grid — Jumper between pin 7 and 8
image164 6
  1. In order for the inverter to synchronize to the grid, a jumper must be added between pin 7 and pin 8.

  2. A core with a cross-section of 0.34 mm2 to 0.75 mm2 is recommended.

12.5.3. AC connection of the FENECON Home 20 & 30-EMS-Box

  • An external 230 V power supply is required to supply the FENECON Home 20 & 30 EMS box.

  • The purpose of this is to avoid straining the empty battery with additional consumer loads. This can occur particularly in winter when there is no sunshine or when there is snow on the PV system.

H20 multiple seal
  1. Feeding the cable through the smaller hole of the multi-hole seal.
    A cross-section of 3 x 1.5 mm2 is recommended.

  2. Make sure that the housing with the 3-hole seal is used.
    The other housing will be needed later.

image114 2
  1. Insert the cable through the bolt connection and the multi-hole seal into the Harting housing.

image114 3
  1. Harting socket insert, 10-pin, with cable.

    • Connect L to 1.

    • Connect N to 2.

    • Connect PE to PE.

image114 4
  1. The other pins are for the integrated relay contacts.
    If these are not used, you can mount the socket inside the housing using bolts.

  2. Close the remaining feedthroughs of the multi-hole seal with the enclosed filler plugs (10 mm) and tighten the bolt connection.

image114 5
  1. Connect the plug to the FEMS box.

  2. Lock the plug at the top and bottom through the holders.

12.6. Explanation of the "zero feed-in" function

Connection and operation of electrical energy storage systems on the low-voltage grid in accordance with VDE-FNN Note 07/2024 — Requirements for the energy flow direction sensor EnFluRi (section 4.3) and zero feed-in (section 4.4).

FENECON GmbH hereby declares that the inverters listed in the following table in combination with the respective energy meters specified fulfill the above requirements:

Inverter

Description

Internal Energy Meter

Home Energy Meter
(FHM-120-C)*

3-Phasensensor ohne Stromwandler
am Netzanschlusspunkt (FHM-C)**

Home 6

FINV-6-2-DAH

(optional)

Home 10 (Gen. 1)

FHI-10-DAH

Home 10 (Gen. 1)

FHI-10-DAH 16A

Home 10

FINV-10-2-DAH

(optional)

Home 15

FINV-15-2-DAH

(optional)

Home 20

FHI-20-DAH

(optional)

Home 30

FHI-29,9-DAH

(optional)

Commercial 50 (Gen. 3)

FINV-50-1-DAH

Commercial 100

FINV-100-1-DAH

*Art.-Nr.: FHO055
**Art.-Nr.: FEH040

12.6.1. Configuration for zero feed-in via the FENECON Energy Management System

The inverters listed above can be configured via the FENECON Energy Management System so that the PV energy generated is used entirely by the user and is not fed-in to the public grid.
To do this, the Maximum feed-in power setting in the commissioning wizard must be set to 0 watts.

12.6.2. Notes on the zero feed-in function:

  • If FENECON inverters are used, deviations of < 1 % per phase may occur.

  • The accuracy of the zero feed-in depends on the power factor of the connected consumer loads.

  • A high proportion of reactive power, especially in the form of harmonics, can negatively affect the accuracy of the active power measurement.

  • With zero feed-in, devices that regulate to PV surplus no longer work, as there is no longer a grid feed-in to which they can regulate.

12.6.3. Validity of the declaration:

This declaration applies to all identical inverters. It loses its validity if:

  • changes have been made to the device,

  • the connection is made improperly,

  • the installation was not carried out in accordance with the installation and service instructions, or

  • the inverter is operated with an external generator.

12.6.4. DC cable from the battery tower to the inverter

This section can be skipped if there are several battery towers.

You will find the installation instructions for 2 or 3 battery towers in the section Electrical installation of additional battery towers.

image115
  1. Use the enclosed DC cable (3 m) for the connection between battery tower and inverter.

  2. Connect the cables to the battery (BAT OUT) and to the inverter (BAT1).

  3. Connect plus (+) to plus (+) and minus (-) to minus (-).

  4. If the DC cables supplied are not long enough, please contact your sales partner.

The DC plugs used on the battery side are not compatible with commercially available MC4 plugs.

The 29.9 kW variant has two battery inputs. The FENECON Home 20 & 30 battery tower must always be connected to battery 1 (BAT1).

12.6.5. Connection and cabling of PV system

image116

The various PV strings can be connected directly to the PV inputs on the inverter.
The 20 kW variant has 2 MPPTs, each with two inputs (red; blue).
The 29.9 kW variant has 3 MPPTs, each with two inputs (red; blue; green)

image116 1

Type 2 overvoltage protection is integrated in the inverter.

12.6.6. Connecting the smart meter to the inverter

image117

Connect the enclosed cable for the meter to the bayonet connection side of the inverter and lock it.
Connect the other end to the meter.
If the existing 10 m cable is not sufficient, it can be extended up to 100 m using a conventional network cable.

12.6.7. Communication between inverter and EMS box

image117 1
  1. Feed the enclosed communication cable (3 m network cable with open end) through one of the holes in the multi-hole seal of the communication port cover.

  2. Leave the other openings of the multi-hole seal closed.

image117 2
  1. Connect the plug of the communication cable to the inverter.

image117 3
  1. Connecting the cover to the inverter and tightening the bolt connection.

H20 multiple seal
  1. Feeding the cable through one of the four holes in the multi-hole seal.

image117 4
  1. Insert the cable through the bolt connection and the multi-hole seal into the Harting housing.

image117 5
  1. The other end with two open pins must be connected to terminal 1/2 on the Harting plug (16-pin — A).

  2. Connect the white core to terminal 1.

  3. Connect the orange core to terminal 2.

If controllable consumer loads have been installed and one of the following FEMS extensions has been purchased, the following two steps can be neglected for the time being.

  • FEMS App Heat pump "SG-Ready"

  • FEMS App CHP

image117 6
  1. Then screw the socket into the Harting housing.

  2. Close the other openings in the bolt connection with the enclosed filler plugs (8 mm).

  3. Provide strain relief for the cable by tightening the bolt connection.

image117 7
  1. Close the remaining feed-throughs of the multi-hole seal with the enclosed filler plugs (8 mm) and tighten the screw connection.

  2. Lock the plug at the top and bottom through the brackets.

12.6.8. Communication from a battery tower

image117 8

If only one battery tower is installed, the jumper plug (included in the scope of delivery) must be plugged into the PARALLEL OUT connection and locked by turning the underside.

You will find the assembly instructions for 2 or 3 battery towers in the section [Communication of additional battery towers].

12.6.9. Communication with the customer network

image119
  1. To seal the network connections, insert the cable into the connector and bolt it in place. Only the multi-hole seal and the bolt connection are required.

If the battery tower is installed indoors, this point can be skipped and the network cable can be connected directly.

image120
  1. Make sure that the network connector protrudes approx. 3 mm beyond the bayonet catch at the front.

  2. For example, the jumper plug of the battery can serve as a reference for the position of the network connector.

image120 2
  1. For internet connection and system configuration, connect the network cable to the LAN port of the battery and the other end of the cable to the customer’s network.

The system does not have a WiFi function.

12.6.10. Plugging the internal input (optional)

image120 1

Optionally, a network connector housing with filler plug (included in the scope of delivery) can be used as a cover for the internal connection. The network connector housing and the filler plug must be fitted beforehand.

An IP classification is only guaranteed if the corresponding plugs are locked on all connections.

13. Parallel connection of several battery towers

13.1. Assembly of further battery towers

13.1.1. Assembly of battery tower 2 with FENECON Home 20 & 30 Parallel box

If a second battery tower is available, the Parallel box is plugged onto the second battery tower instead of the EMS box.

H20 Parallel Top

To do this, repeat the steps from the section Assembly battery tower 1. In step 8, attach the FENECON Home 20 & 30 parallel box instead of the FENECON Home 20 & 30 EMS box.

13.1.2. Assembly of battery tower 3 to 4 with FENECON Home 20 & 30 extension box

If there is a third to fourth battery tower, an Extension box is attached to the third to fourth battery tower instead of the EMS box.

H20 Ext Top

To do this, repeat the steps from the section Assembly battery tower 1. In step 8, attach the FENECON Home 20 & 30 extension box instead of the FENECON Home 20 & 30 EMS box.

13.2. Electrical installation of additional battery towers

13.2.1. DC cable between two battery towers and the Inverter

H20 DC Bat Wr
  1. Use the enclosed DC cable (3 m) for the compound from the second battery tower with the plugged-on Parallel box to the inverter.

  2. If the length of the DC battery cable is not sufficient, extend it using one of the enclosed sets of DC cables (2 m).

  3. Connect the cables to the second battery tower (Parallel box) (BAT OUT) and the inverter (BAT) (red).

  4. Connect plus (+) to plus (+) and minus (-) to minus (-).

  5. The two battery towers are connected to each other using the second set of cables supplied in the Parallel box.

  6. To do this, connect the two cables to the first battery (EMS box) (BAT OUT) and to the second battery (Parallel box) (BAT IN) (green).

13.2.2. DC cable between the third to fourth battery tower and Parallel box

H20 DC Bat Parallel
  1. The third and fourth battery towers are connected to the Parallel box. Depending on the distance, a 2 m cable set is sufficient; if not, the two enclosed cable sets can be compounded and thus extended to 4 m.

  2. To do this, connect the two cables between the Extension box (BAT OUT) and the parallel switch box (BAT IN).

13.3. Communication of further battery towers

13.3.1. Communication between two to four battery towers

H20 DC Ext Parallel
  1. If several battery towers are operated in parallel, the network cable supplied with the Parallel box and Extension box must be used between the towers (green).

  2. The network cable must be plugged in and locked between the EMS box (PARALLEL OUT) and the Parallel box (PARALLEL IN).

  3. Likewise on all other towers, always between PARALLEL OUT and PARALLEL IN (blue/orange).

  4. At the last tower, plug the jumper plug into PARALLEL OUT (red).

14. Initial commissioning

14.1. Checking the installation, connections and cabling

Check the system as follows before initial commissioning:

  • All components (clearances, environment, mounting) are installed correctly.

  • All internal wiring is complete and properly connected.

  • All external supply lines (power supply, communication cable) are properly connected.

  • All connected loads are matched to the system and the necessary settings have been made.

  • All necessary tests of the system were carried out in accordance with the standards.

Commissioning must only be carried out by trained specialist personnel.

  • It is forbidden to disconnect the electrical connectors while they are live. Disconnect the power supply.

  • Batteries must not be connected or disconnected when a current is flowing.

  • Opening batteries is prohibited.

  • Before commissioning the system, ensure that the battery modules are not deeply discharged.

  • If the battery modules are deeply discharged, contact FENECON Service

  • Only charge deeply discharged battery modules as instructed by the FENECON Service.

This is indicated in the installation and service instructions:

  • that an appropriate cooling down period must be observed before starting work on the devices,

  • or that the risk of burns is prevented by wearing suitable protective gloves.

14.2. Switching the system on/off

14.2.1. Switching on the system

WR PV ON
  1. Rack in the EMS box (sub-distribution board or socket).

  2. Rack in the inverter (sub-distribution board, grid and emergency power side).

  3. If available, switch on the PV system with the DC switch on the inverter (left side of the inverter).

Bat Secure On
  1. Racking in the battery tower (front battery tower).

  2. If there are several battery towers, all towers must be racked in.

Bat LED Bar
  1. If commissioning has already been completed, the battery will start and the LED bar should flash after approx. 60 seconds.

  2. The system is now ready for use.

  3. If commissioning has not yet been completed, the battery will not start.
    Configuration via commissioning wizard.

The system is restarted by pressing the push-button on the front of the EMS box. Restarting the system can take up to three minutes.

If the system has not yet been configured, the battery goes into error mode or switches off.
This can also happen during configuration. It is therefore recommended that you only switch on the battery when you are prompted to do so during the configuration process.

The inverter only starts after configuration and only then synchronizes with the grid.

14.2.2. FEMS push-button and LED ring

Table 40. Status of the LED ring on the FEMS box
Dauerhaft

If the blue LED ring of the push-button does not light up, the FEMS box is not supplied with power or the FEMS box is switched off.

Dauerhaft

If there is an internet connection to the FENECON server, the blue LED ring of the push-button lights up permanently.

LED-Ring

If the blue LED ring of the push-button flashes with an interval of 1 second, there is no internet connection to the FENECON server.

Pressing the push-button restarts the FEMS.

14.2.3. Switch off

Bat Secure Off
  1. Racking out the battery tower (front battery tower).

  2. If there are several battery towers, all towers must be fused.

WR PV OFF
  1. If present, switch off the PV system using the DC switch on the inverter.

  2. Rack out the inverter. (sub-distribution board, grid and emergency power side).

  3. Rack out the EMS box (sub-distribution board, or socket).

WR LEDs
  1. The system is only completely switched off when all LEDs on the inverter and the battery are no longer lit. This can take approx. 30 seconds.

  2. The inverter remains on if one of the three energy sources is not switched off.

14.3. Configuration via commissioning wizard

Open www.fenecon.de and click on the login to FENECON Online Monitoring"FEMS-Login" in the top right-hand corner. Alternatively, you can use the QR code below or the link to access the page.

portal

Sofern Sie noch nicht über einen Installateurs-Account verfügen, erfahren Sie hier, wie Sie diesen erstellen.

home cx step 00

After logging in, you will be taken to this screen.
Click on the plus symbol at the bottom center and then on ADD NEW FEMS.
TIP: If you cannot access this screen directly, please click on the burger menu at the top left and then on _All systems
.

home cx step 01
  1. Enter the installer key.
    You can find this on the sticker on the inverter or on the FEMS box.

home cx step 02
  1. Carry out a software update if necessary.

home cx step 03
  1. Select the attachment type, in this case:
    FENECON Home.

home cx step 04
  1. Select the system.

The product names are based on the output of the respective inverter.
home cx step 05
  1. If it is a system with a 6 kW or 10 kW inverter, select here whether an automatic off-grid switch is installed. If yes, the serial number must be entered here manually.

home cx step 06
  1. The contact details of the installer account are automatically transferred.

home cx step 07
  1. Enter the end customer’s contact details here.

The end customer account is created with the e-mail address entered here. The end customer commissioning report is also sent to this address. Both the installer and the end customer will receive a commissioning report by email.
home cx step 08
  1. Enter the location of the storage system here if the system location differs from the customer address (for service purposes).

home cx step 09
  1. Click on VALIDATE.

    • Then select the address found from the list.

The location coordinates are checked here to ensure the functions of location-dependent applications (e. g. weather data).
home cx step 10
  1. If dimming is required at the system location in accordance with § 14a EnWG, you can set this here.

home cx step 11
  1. This is where you activate the emergency power function and, if necessary, the emergency power reserve.

The emergency power reserve can be configured by the end customer at any time afterwards. However, the general emergency power function CANNOT.
home cx step 12
  1. Select the energy flow direction meter ("EnFluRi") here:

    • For Home 6, 10 & 15: Here you can select whether the internal one built into the inverter (standard) is selected, or whether the "small" energy meter is selected if the application requires cables longer than 15 meters. Optional accessories can also be selected here.

    • Explicitly for Home 20 & 30: The standard scope of delivery or the optionally available, FENECON meter for higher currents is selected here.

home cx step 13
  1. Select the pre-fuse of the house connection meter here.

    • Specified in amperes (A).

home cx step 14 2
  1. The connections of the MPP trackers are displayed here for checking purposes.
    Check whether the connections of the MPPT used have been made correctly and confirm that the connections have been checked.

home cx step 15
  1. Configure shade management according to MPP trackers here.

If PV optimizers are used, shade management must be switched off.
home cx step 16
  1. Configure Feed-in management according to the grid operator’s specifications.

home cx step 17
  1. Check the information you have previously entered and confirm the terms and conditions and warranty conditions.

    • The battery and inverter must also be switched on.

home cx step 18
  1. After clicking on START CONFIGURATION the configuration of the system begins.

Leave the battery and inverter switched on during the entire configuration process.
home cx step 19
  1. Select the number of battery towers and modules.

    • Confirm the displayed serial numbers of the system components.

    • The readout may take a few minutes.

In rare cases, serial numbers must be added manually.
home cx step 20
  1. This completes the configuration via the commissioning wizard.

    • The system is now ready for operation.

      • You can now continue with the installation of FEMS Apps by clicking on APP CENTER.

  • You will receive an e-mail with a commissioning report attached for your records.

  • The customer also receives an e-mail with the personal access data for end customer monitoring.

15. FEMS Online Monitoring

The FEMS Online Monitoring is used to visualize all energy flows in your system. The Energy Monitor shows live data on grid withdrawal or feed-in, PV production, charging/discharging of the battery energy storage system and power consumption. Other widgets show the percentage of self-sufficiency and Self-consumption. In addition, the individual widgets offer a detailed view, which can also be used to view the performance values with phase accuracy.

In addition to the pure information display, all additionally purchased FEMS extensions, such as for integrating a heat pump, Heating element, combined heat and power plant (CHP), are also listed in Online Monitoring. Their functionality can be controlled via the corresponding widget.

In addition to the live view, the history offers the option of selecting self-selected time periods for Online Monitoring. The status of the entire system and the individual components can be monitored at any time using the info symbol.

15.1. Access data

Access to FEMS Online Monitoring is separated according to end customer and installer.

15.1.1. Access for the end customer

Access for the end customer is automatically generated once commissioning is complete and sent to the end customer by e-mail.
The terms and conditions still need to be confirmed here, then the monitoring is available without restrictions.

If additional users want to access the system, they must create their own user account. This is done as described in the section Configuration via commissioning wizard, but here "USER" must be selected in the header.

After successfully creating an additional user account, all we need is an email to service@fenecon.de with the email address used and the FEMS number concerned, we will create the link and other users can use the Online Monitoring of a system.

15.1.2. Access for the installer

The installer account can be created as described in the section Configuration via commissioning wizard on the FENECON homepage. Access is required for successful commissioning.

16. Capacity expansion of the system

The capacity can also be expanded at a later date; there is no time limit here.

The maximum capacity is not reached with additional new battery modules, as new modules are equal to the old modules.

16.1. Capacity expansion of the battery tower
by one or more battery modules

The battery tower can be expanded to up to 15 battery modules in one battery tower.

If the electrical energy storage system is expanded with additional battery modules after commissioning, proceed as follows:

After a capacity expansion, the commissioning wizard must be carried out again.

image174
  1. Open the Online Monitoring.

  2. In order for the new modules to synchronize faster with the existing modules, an equal state of charge is required (30 % SoC). The electrical energy storage system automatically prepares itself if the state of charge does not have the same SoC.

image177 1
  1. Click on the "Electrical energy storage system" widget in Online Monitoring.

image177 2
  1. Activate the "Capacity expansion" function in Online Monitoring under Electrical energy storage system. The "Capacity expansion" is activated when the blue bar is displayed.

  2. You can now choose between "Immediate start" and "Planned extension". With the two options, the battery is charged or discharged to 30 %.

  3. When the state of charge is reached, charging/discharging is stopped and the charge level of 30 % is maintained.

image177 3
  1. If you select "Planned extension", you can specify the planned day and time. In this example, 24.05.2024 and the time of 09:00 were selected. At this time, the battery is expected to be charged or discharged to reach 30 % for the "Planned extension".

image177 4
  1. You must then confirm your desired settings by clicking on the blue tick. The desired extension will be saved and, depending on the option selected, implemented immediately or later at a specific time.

image145
  1. Then run the commissioning wizard again.

The capacity can also be extended at a later date; there is no time limit here. You will not reach the full capacity with the new battery module, as the new module will equalize with the old modules.

If the battery tower is extended by additional battery modules after several weeks or months, the following procedure must be followed:

29-30 % SoC

  1. Charge/discharge the system to a charge level of 29-30 %; then switch off.

Bat Secure Off
  1. Switch off the entire system. The exact procedure is described in the section Switching the system on/off.

    • Set the battery fuse switch to OFF.

    • DC switch of the inverter to OFF. AC fuse on the grid and emergency power side to OFF.

image132
  1. Remove the top three side panels on each side.

  2. Remove the latch up to the first battery module on both sides.

image133 134
  1. Remove the FEMS box and BMS box and place them on their side. To do this, screw the wall bracket of the BMS box from the wall.

image081
  1. Attach new battery module.

image133 134
  1. Proceed as described in section Assembly of battery tower 1 with FEMS box, step 8.

    • Attach the FENECON BMS box.

    • Attach the FEMS box.

    • Attach the locks.

    • Attach the side covers.

  • If the exact voltage value of the old and new battery modules has not been matched, SoC jumps will occur when the battery is charged and discharged. This means that the full capacity is temporarily not available.

  • The greater the voltage difference between the "old" and "new" batteries, the longer it can take until there are no more SoC jumps and the full capacity is available.

16.2. Capacity expansion of the system
by one or more battery towers

The capacity of the system can be subsequently expanded by one or more battery towers with the same capacity. There is no time limit here.

The maximum expansion of the FENECON Home 20 & 30 system comprises up to 4 battery towers, each with 4 to 15 battery modules and a maximum of 168 kWh.

The full capacity is not achieved with new battery modules, as the new modules become similar to the old modules.

Proceed as follows before the extension:

image147
  1. Activate the "Capacity expansion" function in Online Monitoring under Electrical energy storage system.

  2. The battery is charged/discharged to 30 %. When the state of charge is reached, charging/discharging is stopped and the charge level is maintained.

image0138
  1. Switch off the entire system. The exact procedure is described in detail in the section Switch off. → Fuse switch of the battery to OFF. + → AC fuse of the inverter to OFF.

image0152
  1. Assembly of the new battery towers as described from section Assembly — Battery tower 1 with FEMS box and section Initial commissioning.

  2. Everything can then be switched on again as described in the Switching on the system section.

image145
  1. Run the commissioning wizard again.

  • If the exact voltage value of the old and new battery towers has not been matched, the new batteries will not be connected.

  • This is not displayed as an error, but it can happen that the SoC displays of the individual battery towers show different charge levels.

  • When the charge levels have equalized after a charging cycle, the last battery towers also switch on.

  • The battery towers work independently, so the flashing frequency of the different towers may vary. The SoC display of the individual towers may also differ briefly.

17. FEMS extensions

For the following FEMS extensions, the integrated relays can be used directly on the (first) battery tower.
Various pins on the Harting plugs are provided for this purpose.

  • Harting plug 10-pin: 3 x free relay channels (max.: 230 V; 10 A)

  • Harting plug 16-pin: 2 x control contacts (max.: 24 V; 1 A)

    • 3 x digital input

    • 1 x digital input for § 14a

    • 1 x analog output (0-10 V)

It may not be possible to connect and operate all apps at the same time.
For more information on the following apps, please visit our homepage.

If the integrated relays are not sufficient, an external 8-channel relay board can be connected via Ethernet.

Harting Pinout 20 30

The pin assignment of the Harting plug (10-pin) is shown in detail below.

Table 41. Connector — Pin assignment — Power connector
Item Description

1

230 V supply for internal components

2

Relay 1 (230 V; 10 A)

3

Relay 2 (230 V; 10 A)

4

Relay 3 (230 V; 10 A)

5

Neutral conductor connection (required for integrated meter)

6

PE connection

Harting pinout detailed

The pin assignment of the Harting plug (16-pin) is shown in detail below.

Table 42. Connector — Pin assignment: Control connector
Item Description

1

RS485 connection — Inverter

2

RS485 connection — External devices

3

Analog output (0 to 10 V)

4

12 V DC (12 V; GND)

5

3 x digital inputs

6

Digital input for § 14a

7

Relay 5 (24 V; 1 A)

8

Relay 6 (24 V; 1 A)

9

PE connection

17.1. Connection of a heat pump via "SG-Ready"

The integration of an "SG-Ready" (Smart Grid-ready) heat pump is an advanced form of sector coupling of electricity and heat - often also referred to as a "power-to-heat" application. The control system ensures that the heat pump slightly overheats the thermal energy storage system at times when cheap (solar) electricity is available in order to save electrical energy at times when there is no cheap surplus electricity.

harting heating element
  1. The internal relay contacts 5 and 6 can be connected via pins 5/6 and 7/8 on the Harting plug (16-pin — C).

  2. For detailed information on connecting the heat pump, please refer to the manufacturer’s installation instructions.

After installing the components, the app still needs to be installed.
To do this, proceed as described in the section Activation of the app in the FEMS App Center.

17.2. Connection of a heating element with a maximum of 6 kW

The integration of an electric heating element is the simplest and cheapest form of sector coupling of electricity and heat — often also called a "power-to-heat" application.

If the capacity of the electrical energy storage system is exhausted, self-generated energy must be fed into the public grid with low remuneration. In these cases, it often makes sense to use the surplus current for water heating (e. g. for hot water buffer tanks, pool heating, etc.). This way, other energy sources (e. g. wood or oil) can be saved.

heatingelement 6kw
  1. So that each phase of the heating element can be controlled separately, each phase must be connected individually to a relay.

  2. To do this, connect phase 1 (brown) to pin 3 on the Harting plug (10-pin). Continue from pin 4 to the heating element. Use pins 5/6 and 7/8 for phase 2 (black) and phase 3 (gray).

  3. Loop through the neutral conductor N via pin 9/10.

  4. A cable (5G1.5) from the sub-distribution board to the Harting plug and a cable (5G1.5) from the Harting plug to the heating element are recommended.

  5. For detailed information on connecting the heating element, please refer to the manufacturer’s installation instructions.

Ensure that three different phases are used. If only one phase is used, damage may occur.

After installing the components, the app still needs to be installed.
To do this, proceed as described in the section Activation of the app in the FEMS App Center.

Manual mode is only suitable for temporary operation. For permanent operation, the external relay control must be used.

17.3. Control of a heating element greater than 6 kW
(control via external relay)

Die extern installierten Relais müssen nach der installierten Leistung des verbauten Heizstabes ausgelegt werden.
heatingelement 6kw 3p
  1. So that each phase of the heating element can be controlled separately, each phase must be connected individually to the internal relay via an additional external relay.

  2. Connect L1 to pin 3 via a MCB B6 fused. Route phase L1 from pin 4 to the external relay and connect to A1. A2 must be connected to neutral.

  3. Proceed in the same way as step 2 with the other two phases. Connect K2 and K3 via pins 5/6 and 7/8.

heatingelement 6kw 1p
  1. As an alternative to L2/L3, L1 can of course also be looped through, or:

  2. Alternatively, control the contactors/relays with 24 V. If another voltage source is used, do not connect A2 to N.

heatingelement 6kw relais
  1. The power supply of the heating element must then be connected to the switching contacts of the relays.

  2. For detailed information on connecting the heating element, please refer to the manufacturer’s installation instructions.

After installing the components, the app still needs to be installed.
To do this, proceed as described in the section Activation of the app in the FEMS App Center.

17.4. Controlling a CHP unit

The integration of a combined heat and power plant (CHP) into electrical energy management is an advanced form of sector coupling of electricity and heat.

This allows using the CHP as an electrical generator that is independent of the time of day and weather conditions. When the state of charge of the electrical energy storage system is low, the CHP is given a switch-on signal to produce electricity. This is useful, for example, if the battery capacity is not sufficient to cover electricity consumption at night. This avoids the need to purchase expensive current from the grid.

When the battery is charging, this signal is stopped again to prevent the CHP’s current from being fed into the grid unnecessarily.

harting heating element
  1. The enable signal for starting the CHP can be connected to pins 5/6 via the Harting plug (16-pin — C).

  2. For detailed information on connecting the CHP, please refer to the manufacturer’s installation instructions.

After installing the components, the app still needs to be installed.
To do this, proceed as described in the section Activation of the app in the FEMS App Center.

17.5. Additional AC meter

  • If additional meters have been installed for monitoring other consumer loads or generators, these must be integrated into the circuit in accordance with the manufacturer’s instructions.

  • The communicative integration is shown below using a 3-phase sensor without a current transformer as an example.

  • Only meters approved by FENECON can be integrated.

  • The first production meter is always integrated with Modbus ID 6. All others in ascending order. The baud rate is 9600.

additional ac meter 1
  1. Connect the cores to pin 3/4 on the Harting plug (16-pin — A).

  2. Connect the white core (alternative color possible) to terminal 3.

  3. Connect the brown core (alternative color possible) to terminal 4.

additional ac meter 2

For example SOCOMEC E24

  1. The brown wire (alternative color possible) is connected to the meter at connection point 2 and the white core (alternative color possible) is then connected to 3.

  2. A terminal resistor with 120 Ω must be installed between (+) and (-) (A/B) on the last bus device.

additional ac meter 3

For example KDK 4PU

  1. The brown wire (alternative color possible) is connected to the meter at connection point 8 and the white core (alternative color possible) is then connected to 7.

  2. A terminal resistor with 120 Ω must be installed between (+) and (-) (A/B) on the last bus device.

If several meters are to be installed, they can be connected in series for communication purposes. For this purpose, the first meter can be bridged to the second, etc. The Modbus address must be set in ascending order.
Link to the overview page of the installation and configuration instructions for energy meters

Once the components have been installed, the app still needs to be installed.

17.6. Activation of the app in the FEMS App Center

After installing the hardware FEMS App extension, it still needs to be activated in the App Center. To do this, proceed as follows:

QR code link to the FENECON portal
installer login
  1. Log in with your installer account.

First check whether updates are available for the FEMS.

18. Updating the FEMS

To be able to use all FEMS Apps extensively and in the latest version, carry out a system update to the latest version.

  1. Open the burger menu at the top left of FENECON Online Monitoring.

Tap/click burger menu
Illustration 28. Burger to side menu — System update — Step 1
  1. Select Settings.

FENECON Online Monitoring,  Einstellungen
Illustration 29. Side menu — System update — Step 2
  1. Select FEMS System.

FEMS-Systemupdate
Illustration 30. App Center — System update — Step 3
  1. Click on INSTALL LATEST VERSION to update the system. If the latest version is already installed, you do not need to do anything else.

Neuste,  Version installieren
Illustration 31. App Center — System update — Step 4
To return to the settings menu after the FEMS system update:
Click on the arrow at the top left. This applies to all submenus in the Settings area.
Pfeil,  zurück
Illustration 32. Back to the Settings menu

19. Starting point: FEMS App Center

  1. After you have performed a system update, open the FEMS App Center.

    1. Alternatively, go to the FEMS App Center via the top left burger menu in the FENECON Monitoring.

App,  Center
Illustration 33. App Center — Step 1
  1. You are now in the App Center. From here you can redeem and register licence keys for apps, install new apps and edit or subsequently configure apps that are already installed.

App,  Center 2
Illustration 34. App Center — Step 2

19.1. Installation of further FEMS Apps

The following instructions show an example of how to install an FEMS App PV inverter.

There are two ways to install an FEMS App via the App Center.

19.1.1. Installation after redeeming a licence key

After a licence key has been redeemed, a selection of available apps that can be installed is displayed.

The App Center offers a search bar and a filter option to get to the desired app more quickly:

App-Suche
Illustration 35. Search for a specific app in the App Center

In the example, the FEMS App SMA PV Inverter was searched for. This app is selected by clicking or tapping on the tile.

FEMS,  App SMA PV Inverter installieren
Illustration 36. App installation — Variant 1 — Step 1

You will then be taken to the app overview:

FEMS,  App SMA PV Inverter Vorschau
Illustration 37. App installation — Variant 1 — Step 2

Select the INSTALL APP button.

You will then be taken to the installation wizard for the respective app:

FEMS,  App SMA PV Inverter — Installationsassistent
Illustration 38. App installation — Variant 1 — Step 3

Some of the input fields are pre-filled. Nevertheless, enter your data if it differs from the default values (e. g. IP address). Otherwise, the default values can be retained (e. g. port, Modbus unit ID).

Mandatory fields are marked with (*)
Check your entries and make sure that they are correct. Otherwise the respective app will not work properly!

Select the INSTALL APP button again.

Once the installation process has been successfully completed, the new app will appear in the App Center overview in the Installed category.

FEMS,  App SMA PV Inverter wurde erfolgreich installiert
Illustration 39. App installation — Variant 1 — Step 4

19.1.2. Direct installation

You can also install an app directly. To do this, go to the App Center overview and search for the desired app.

Only apps from the "Available" category can be installed.
App-Suche
Illustration 40. Search for a specific app in the App Center

In the example, the FEMS App SMA PV Inverter was searched for. This app is selected by clicking or tapping on the tile.

FEMS,  App SMA PV Inverter installieren
Illustration 41. App installation — Variant 2 — Step 1

You will then be taken to the individual view of the app:

FEMS,  App SMA PV Inverter Vorschau
Illustration 42. App installation — Variant 2 — Step 2

Select the INSTALL APP button.

An input mask for redeeming a licence key appears:

Lizenzschlüsselvalidierung
Illustration 43. App installation — Variant 2 — Step 3

You have two options here:

Redeem a new licence key directly

If you have not yet registered a licence key or wish to redeem a new licence key, enter the 16-digit key in the corresponding field and then click on VALIDATE LICENCE KEY.

The entered licence key is then checked for validity.

redeem new key
Illustration 44. Redeem new licence key directly

If the licence key is valid, it can be registered by clicking on the button of the same name.
REDEEM LICENCE KEY

If the licence key is invalid, please check your entry and try again.
Redeem an already registered licence key

In this case, the button in the App Center looks like this:

Eine,  installationsbereite Lizenz

If you want to redeem an already registered licence key, check the corresponding box and select the appropriate, already registered licence key via drop-down menu.

Bereits registrierten Lizenzschlüssel einlösen
Illustration 45. Redeem already registered licence key

Then click on the REDEEM LICENCE KEY button.

You will then be taken to the installation wizard for the respective app.

FEMS,  App SMA PV Inverter — Installationsassistent
Illustration 46. App installation — Variant 2 — Step 4

Some of the input fields are pre-filled. Nevertheless, enter your data if it differs from the default values (e. g. IP address). Otherwise, the default values can be retained (e. g. port, Modbus unit ID).

Mandatory fields are marked with (*)
Check your entries and make sure that they are correct. Otherwise the respective app will not work properly!

Select the INSTALL APP button again.

Once the installation process is complete, the new app will appear in the App Center overview in the Installed category.

FEMS,  App SMA PV Inverter wurde erfolgreich installiert
Illustration 47. App installation — Variant 2 — Step 5

20. External control of the inverter

There are various ways to override the inverter from external devices.

energy journey curtailment 01
Illustration 48. Connection — Curtailment via ripple control receiver

20.1. Ripple control receiver at the AC output

The inverter can be controlled directly via a ripple control receiver. The following plugs supplied with the inverter are required for this.

H20 Wr Plugs
  1. The inverter’s small parts box contains three plugs that can be plugged into the underside of the inverter.

H20 Wr Plugs pinout
  1. The plugs are numbered consecutively.

image164 3
  1. In order for the functions to be activated, activate the ripple control receiver during commissioning.

  2. Then confirm with OK.

The active power of the FENECON Home 20 & 30 inverter can be controlled directly by the energy supply company (grid operator) via a ripple control receiver (RCR).
The behavior of the inverter in the various control stages can be described as follows.

  • 100 % → Standard signal, inverter works without restrictions (20/30 kW)

  • 60 % → Inverter output power is reduced to 60 %. (12/18 kW)

  • 30 % → Inverter output power is reduced to 30 %. (6/9 kW)

  • 0 % → Inverter output power is reduced to 0 %. (0/0 kW)

If other inverters are used, these must also be connected separately to the RCR; how exactly depends on the grid operator and the RCR used.

In the event of a curtailment to 0 %, the grid feed-in of the inverter is stopped completely, i.e. the consumer loads are supplied completely from the grid.
Only the battery continues to be charged.

image164 4
  1. A cable with at least 5 cores with a cross-section of 0.34 mm2 to 0.75 mm2 is recommended.

  2. Feed the cable through one of the holes of the multi-hole seal.

  3. Attention: One feedthrough is already blocked by the communication cable between the inverter and EMS.

  4. Leave the other openings of the multi-hole seal closed.

image164 5
  1. Connect the cores of the control cable as shown in the picture.

image164 6
  1. In order for the inverter to synchronize to the grid, a jumper must be connected between pin 7 and pin 8.

  2. A core with a cross-section of 0.34 mm2 to 0.75 mm2 is recommended.

image164 7
  1. Plug in the two connectors on the underside of the inverter.

image164 8
  1. Attach the cover to the inverter and tighten the bolt connection.

20.2. Ripple control receiver on grid connection point

The system can be controlled directly via the ripple control receiver (RCR).

Observe the specifications of your grid operator when connecting the external radio ripple control receiver.

If other inverters are used, these must also be connected separately to the RCR; how exactly depends on the grid operator and the RCR used.

The behavior of the inverter in the various control stages can be described as follows:

  • 100 % → Standard signal, inverter works without restrictions (20/30 kW).

  • 60 % → Feed-in power at the grid connection point is reduced to 60 % (12/18 kW).

  • 30 % → Feed-in power at the grid connection point is reduced to 30 % (6/9 kW).

  • 0 % → Feed-in power at the grid connection point is reduced to 0 % (0/0 kW).

When connecting to the FEMS box, the following contacts must be connected in the Harting connector:

H30 Harting connection RCR
Illustration 49. Connection — Ripple control receiver on GCP — Home 20 & 30

During commissioning, the dynamic ripple control receiver must be selected under External limitations:

fems dyn RCR

The ripple control receiver now regulates the grid limitation to the grid connection point and no longer to the AC output. This means that it is also possible to charge the battery and supply the consumer loads with PV production in the event of grid limitation.

energy journey curtailment 02
Illustration 50. Connection — Curtailment via ripple control receiver

20.3. Remote shutdown

The inverter can be disconnected from the grid when remote disconnection is activated, e. g. via a central grid and plant protection. One of the following plugs supplied with the inverter is required for this.

H20 Wr Plugs
  1. The inverter’s small parts box contains three plugs that can be plugged into the underside of the inverter.

H20 Wr Plugs pinout
  1. The plugs are numbered consecutively

IBN NA Schutz
  1. To activate the functions, the remote switch-off must be activated during commissioning.

  2. Then confirm with OK.

  3. Continue to the next step with Next.

The emergency power output is still active (if activated) and supplies the emergency power to the consumer loads.

FRE cover
  1. A cable with 2 cores and a cross-section of 0.34 mm2 to 0.75 mm2 is recommended.

  2. Feed the cable through one of the holes in the multi-hole seal of the cover.

  3. Attention: One feedthrough is already blocked by the communication cable between the inverter and EMS.

  4. Leave the other openings of the multi-hole seal closed.

NA Anschluss
  1. The core of the disconnection device must be connected to pin 7 and pin 8 so that the inverter can be disconnected from the grid.

  2. The switch-off device must be equipped with a break contact
    → In normal operation, pins 7 and 8 must be bridged via the switch-off device.

NA Anschluss 7 Pol
  1. Plugging in the 7-pin connector on the underside of the inverter.

Abdeckung FRE gesteckt
  1. Attach the cover to the inverter and tighten the bolt connection.

This method can also be used to connect P,ave monitoring.

20.4. Section 14a of the Energy Industry Act (EnWG)

The inverter can be limited to a maximum reference power of 4.2 kW. The digital input of the EMS must be assigned for this.

image00190 steuerbox
  1. The signal can be connected to pins 1 ( C ) and 8 ( A ) via the Harting plug (16-pin — A & C).

  2. For detailed information on connecting the FNN control box, please refer to the manufacturer’s installation instructions.

21. Troubleshooting

21.1. Errors in Online Monitoring

The system status can be checked after logging in at the top right using the color of the icon. A green tick indicates that everything is OK, an orange exclamation mark indicates a warning (Warning) and a red exclamation mark indicates an error (Fault).

21.1.1. Fault display

ok

System status: Everything is OK

warning

System status: Warning

error

System status: Error (Fault)

21.1.2. Troubleshooting

image169

You can get a detailed overview of an existing warning or error by clicking on the exclamation mark in the top right-hand corner.

image170

The scroll bar can be used to examine the origin of the warning or error in more detail.
In this example, the error lies with the controller used.

image171

Clicking on the icon (down arrow) displays a more detailed error description depending on the error.

In the example above, an incorrect reference for the grid meter was intentionally entered for test purposes, which is why the controller execution fails.

image172

Under certain circumstances, it may happen that the FEMS is not accessible and the error message opposite appears.

If the FEMS is offline, follow the steps displayed below the message.

21.2. FENECON Home 20 & 30 inverter

21.2.1. Fault display

Faults are indicated by a red LED next to "SYSTEM".

WR LEDs
Illustration 51. Fault display on the FENECON Home 20 & 30 inverter

21.2.2. Rotary field of the grid connection

  • Check whether a clockwise rotating field is present at the grid connection.

  • Otherwise, contact the FENECON Service. You can find the contact details in the Service section.

The LEDs display further information on the status of the inverter.

Table 43. LED status displays — Inverter
Display Status Description
standby symbol
led yellow on

The inverter is switched on and in standby mode.

led green blink

The inverter is starting and is in self-test mode.

led green on

The inverter is running normally in grid-parallel or stand-alone mode.

led red blink

Overloading of the RESERVE output.

led red on

An error has occurred.

led off

The inverter is switched off.

socket symbol
led yellow on

The grid is abnormal and the inverter is in stand-alone mode.

led green on

The grid is normal and the inverter is in parallel mains operation.

led off

RESERVE is switched off.

antenna
led off

The inverter is not connected to the internet. Communication takes place via the EMS box.
Therefore, there is no LED indication here.

21.3. Battery tower

21.3.1. Fault display

Faults are displayed on the BMS box via a red LED.

The various errors are indicated by LED codes.

Speicher-Status

Speicher-Information

LEDs

blau/rot

1

2

3

4

Bootloader

Starten

Master/Slave

Parallel-Box

Extension-Box

Prüfmodus

Einzel- oder Parallelverschaltung

SoC-Display

Laden

0 % bis 25,0 % SoC

25,1 % bis 50,0 % SoC

50,1 % bis 75,0 % SoC

75,1 % bis 99,9 % SoC

100 % SoC

Entladen und Standby

100%-75,1%

75,0%-50,1%

50,0%-25,1%

25,0%-0%

Fehler

Überspannung

Unterspannung

Übertemperatur

Untertemperatur

Überstrom

SoH zu tief

Int. Kommunikation

Ext. Kommunikation

Adressfehler Parallel

Adressfehler Module

BMS-Box-Sicherung

Modulsicherung

Kontaktfehler

Isolationsfehler

BMS-Fehler

Blue permanently on

Blinking blue

Blue flashing quickly

Red permanently on

21.3.2. Troubleshooting

If faults cannot be rectified or in the event of faults that are not included in the fault list, contact FENECON Service. Cf. Service.

21.4. Fault list

Table 44. Troubleshooting
Component Error/fault Measure

Battery module

The battery module has become wet

Do not touch
Contact FENECON Service immediately for technical support

Battery module

The battery module is damaged

A damaged battery module is dangerous and must be handled with the utmost care.
Damaged battery modules must no longer be used.
If you suspect that the battery module is damaged, stop operation and contact FENECON Service

21.5. Service

If the system malfunctions, contact the FENECON Service:

Phone: +49 (0) 9903 6280-0

Our service hours:
Mon.-Thurs. 08:00 to 12:00 | 13:00 to 17:00
Fri. 08:00 to 12:00 | 13:00 to 15:00

22. Technical maintenance

22.1. Tests and inspections

When carrying out inspection work, ensure that the product is in a safe condition. Improperly performed inspections can have serious consequences for people, the environment and the product itself.

Inspection work must only be carried out by trained and qualified specialists.

The maintenance instructions of the component manufacturer must be observed for all individual components.

Kontrollieren Sie das Produkt und die Leitungen regelmäßig auf äußerlich sichtbare Beschädigungen. Bei defekten Komponenten kontaktieren Sie den FENECON-Service. Reparaturen dürfen nur von der Elektrofachkraft vorgenommen werden.

22.2. Cleaning

Cleaning agents: The use of cleaning agents can damage the electrical energy storage unit and its parts.
It is recommended that the electrical energy storage unit and all its parts are only cleaned with a cloth moistened with clean water.

The entire product must be cleaned regularly. Only appropriate cleaning agents must be used for this purpose.
The cleaning agents must be free of chlorine, bromine, iodine or their salts. Steel wool, spatulas and the like must not be used for cleaning under any circumstances. The use of unsuitable cleaning agents can lead to external corrosion.

22.3. Maintenance work

An der Anlage müssen keine regelmäßigen Wartungsarbeiten durchgeführt werden. Prüfen Sie dennoch regelmäßig den Status Ihres Speichers.

Regular re-referencing of the electrical energy storage system is recommended, i.e. it must be completely discharged (SoC = 0 %) and then fully charged again (SoC = 100 %), as otherwise capacity may be lost.

22.4. Repairs

Bei defekten Komponenten muss der FENECON-Service kontaktiert werden.

22.5. Garantiefälle

Garantiefälle sind innerhalb des Garantiezeitraums in Textform (bspw. per E-Mail) an FENECON zu melden. Die Meldung muss innerhalb einer Ausschlussfrist von 8 Wochen erfolgen, nachdem der Endkunde Kenntnis von dem Garantiefall erlangt hat oder ohne grobe Fahrlässigkeit hätte erlangen können.

23. Advice for fire departments when dealing with FENECON Home & Commercial systems

The FENECON Home and Commercial systems operate in the low-voltage range, which means that they are operated with voltages of less than 1,500 volts direct current (DC) and less than 1,000 volts alternating current (AC).

It may be useful to install an additional switch that disconnects the building from the emergency power supply. This makes it easier for the fire department to act safely and quickly in an emergency.

image092
Illustration 52. Installation — Maintenance switch using the example of Home 20/30

For a precise procedure for emergency services, it is recommended to ask the relevant fire academies and request the corresponding information sheets and pocket cards for battery energy storage systems.

24. Flood safety measures FENECON Home & Commercial

First steps after the water has receded

Even if your battery energy storage system looks undamaged on the outside:

  • Do not put the system back into operation yourself.

  • Ventilate the room well before entering (open windows from the outside if possible).

  • Avoid sparks (no smoking, no lighters).

Why a review is important:

Even though LFP batteries are very safe, water or moisture can:

  • Cause short circuits in the electronics.

  • Trigger corrosion of electrical connections.

  • Create isolation problems that only become apparent later.

These problems do not have to occur immediately, but can develop over weeks.

Commission a professional inspection

Please contact:

  • Your installer or a qualified electrician with experience in battery energy storage systems.

  • FENECON, the manufacturer of your system.

  • Your insurance company — document the damage with photos.

The qualified specialist will check:

  • Whether water has entered the system.

  • Whether electronic components have been damaged.

  • Whether a recommissioning is safely possible or a replacement is necessary.

No recommissioning without approval

Battery energy storage systems that have come into contact with water must only be put back into operation after a professional inspection and express approval by a qualified specialist. This is for your safety and is often also a prerequisite for your insurance cover.

When replacement is necessary

If your electrical energy storage system needs to be replaced:

  • The disposal of the defective system must be carried out professionally by specialized companies.

  • Your installer will usually organize the removal and disposal.

  • Do not attempt to transport damaged batteries yourself

Storage disposal until collection

If damaged battery modules cannot be collected immediately:

  • Store them well ventilated outdoors with sufficient clearance from flammable materials.
    Storage in a

    • Sand bed.

    • Fireproof container, not gas-tight, ventilated.

    • Water bath, e. g. metal tub, completely covered with water.

  • Keep children and pets away.

25. Handover to the operator

25.1. Information for the operator

The following information must be provided to the operator:

Table 45. Information for the operator
Component Information/Document Comment

System

FEMS number

System

Login data for Online Monitoring

System

Operating instructions

26. Transport

This section contains information on external and internal transportation of the product.

Transportation is the movement of the product by manual or technical means.

  • Only use suitable and tested lifting gear and hoists for transportation!

Risk due to lifted loads!
Standing under suspended loads is prohibited!

Check that the parts and outer packaging are in perfect condition.

Check that

  • all screw and bolt connections are tightened firmly,

  • the transport rail has been properly attached,

  • you wear personal protective equipment (PPE).

  • Ensure that nobody is on or near the product during transportation. Do not use people as counterweights.

  • Ensure that nobody is below suspended loads.

Notes:

  • The batteries are removed or replaced by specialist personnel and transported by a hazardous goods carrier.

  • When transporting the batteries, observe the current laws, regulations and standards, e. g. the Hazardous Goods Transportation Act (GGBefG).

Legal regulations
The product is transported in accordance with the legal regulations of the country in which the product is transported off-site.

27. Dismantling and disposal

27.1. Prerequisites

  • The power supply to the electrical energy storage unit is interrupted and secured against being switched on again.

Sharp and pointed edges
Injuries to the body or limbs caused by sharp and pointed edges.

  • Always wear suitable protective equipment (cut-resistant protective gloves, protective footwear, protective eyewear) when working on the product!

27.2. Dismantling

  • The electrical energy storage system may only be dismantled by authorized qualified electricians.

  • Dismantling work must only be carried out when the system has been taken out of operation.

  • Before starting disassembly, secure all components to be removed against falling, tipping over or moving.

  • Dismantling work must only be carried out when the system is shut down and only by service personnel.

  • The dismantling instructions of the component manufacturer (→ Appendix, Applicable documents) must be observed.

  • When transporting the battery modules, the current laws, regulations and standards must be observed (e. g. Dangerous Goods Transportation Act — GGBefG).

27.3. Disposal

  • The FENECON electrical energy storage system must not be disposed of with normal household waste.

  • The FENECON electrical energy storage system is RoHS and REACH compliant.

  • Disposal of the product must comply with local regulations for disposal.

  • Avoid exposing the battery modules to high temperatures or direct sunlight.

  • Avoid exposing the battery modules to high humidity or corrosive atmospheres.

  • Dispose of the electrical energy storage system and the batteries it contains in an environmentally friendly manner.

  • Contact FENECON GmbH to dispose of the used batteries.

  • For the disposal of all components, the usual procedures at the site and the applicable environmental protection regulations must be applied!

  • For the disposal of auxiliary and operating materials, observe the local regulations and information from the safety data sheets.

  • For disposal, please also observe the information in the individual operating instructions for the respective components.

  • If in doubt about the disposal method, contact the manufacturer or the local waste disposal company.